EMERGENCY WATER OUTAGE
Apr 29, 2026 | 11:30 AM

EMERGENCY WATER OUTAGE
Apr 29, 2026 | 10:55 AM

DC Water Releases Key Findings on Extent of Sewer Overflow and Potomac River Impact

February 06, 2026
Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor located along the Clara Barton Parkway at the 495 interchange and C & O Canal National Historical Park. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates that approximately 243 million gallons of wastewater has overflowed from the collapse site. The vast majority of this volume, approximately 194 million gallons, occurred within the first five days, prior to the overflows being significantly reduced through bypass pumping operations.

Analysis of Potomac River flow data indicates that the estimated peak discharge of wastewater, approximately 40 million gallons per day, represents about 2% of the Potomac River’s total flow during that period.  

Ongoing water quality monitoring continues to show improving conditions downstream of the discharge point near Lock 10.   Since February 1, E. coli concentrations at all downstream sampling locations have remained within the US Environmental Protection Agency’s acceptable range for primary contact recreational activities, apart from a single day at Fletcher’s Boathouse.

Sampling within the drainage channel where the overflow occurred continues to show elevated E. coli levels. This is not unexpected, given intermittent residual discharges and snowmelt carrying remaining wastewater from the creek bed into the channel. Concentrations in this area are expected to fluctuate until residual material is fully flushed and baseline conditions are restored.

Efforts to reach the collapse site and finalize the repair strategy remain challenging due to the discovery of a rock dam inside the interceptor, which is significantly restricting internal access. DC Water is implementing a revised construction and repair approach that is expected to take 4-6 weeks and includes:

  • Construction of a new bypass pump location to enable the safe removal of rock at the collapse site.
  • Creation of a new upstream access point to facilitate repairs and enhance worker safety.
  • Development of a new downstream connection to the Potomac Interceptor to improve wastewater conveyance and reduce future risk.
  • Installation of an upstream bulkhead to restrict wastewater flow to the damaged section as much as possible.

In the interim, the existing bypass system remains operational and is successfully diverting wastewater around the damaged pipe section and back into the Potomac Interceptor. Some limited overflows have occurred, primarily due to increased wastewater flow associated with snowmelt and brief pump maintenance and operational issues. For example, during overnight pump maintenance, up to 300 gallons of wastewater escaped but was contained and did not reach the Potomac River.

Until full functionality is restored to the Potomac Interceptor, there remains a residual risk of additional limited overflows.  However, both the likelihood and volume of any future releases are expected to remain minimal.

DC Water continues to coordinate with federal, state and local partners, including Maryland Department of the Environment, DC Department of Energy and Environment, U.S. Environmental Protection Agency, public health officials, and other stakeholders. This coordination includes daily reporting, environmental impact evaluation, and development of remediation measures as appropriate.

Below are the latest results of water quality samples, utilizing a contracted environmental firm and certified laboratory, DC Water initiated daily sampling for E. coli, an indicator bacterium, at six (6) locations beginning on Jan 29, 2026. To assess water quality conditions, sampling locations including the overflow area as well as upstream and downstream sites.  The locations are shown on the following map, and the results are provided in the table below.

Water Quality Sampling Locations

map of sampling sites

Water Quality Sampling Results

chart of water quality test results

Consistent with public health and U.S. Environmental Protection Agency standards, E. coli levels below 410 MPN/100 mL are considered acceptable for primary contact recreational activity.

Historical data indicate typical levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges. 

Latest News

A section of the canal where the soil has been removed
  • Crews are close to completing the removal of remaining soil from Locks 11 to 13 in the section of the C&O Canal that was used as an emergency bypass after the collapse of the Potomac Interceptor sewer ...
Excavation site outside the I-495 Beltway showing section of the PI

Crews completed cleaning on Lock 11 of the C & O Canal as prescribed by the National Park Service, with soil removal also nearing completion within the lock area. Tree removal is also underway, after DC Water received the permits to move forward as part of the site preparations for the long-term accelerated rehabilitation of more than 2700 linear feet of the Potomac Interceptor sewer line that had been previously planned.

Photo of long stretch of C & O Canal with soil removed

DC Water has excavated a section of the Potomac Interceptor along Clara Barton Parkway, outside the I-495 Beltway as part of the accelerated rehabilitation of more than 2700 linear feet of the interceptor that was previously planned. As part of the long-term rehabilitation project, crews are beginning to remove trees which is necessary to construct a bypass chamber that will divert wastewater around sections of the pipe while they are being rehabilitated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The shields for the tunnel boring machine Mary being lowered by cranes into the shaft
DC Water Earns Prominent Award for Sustainable Finance Leadership through Green Bonds

Recognition highlights DC Water’s commitment to environmental stewardship during Earth Month

DC Water has been honored with the “Green Bond of the Year – US Muni Bond” Award by Environmental Finance, a leading industry publication. This achievement celebrates DC Water’s leadership in sustainability and its dedication to responsible municipal financing.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
May 5, 2026
Tuesday, 1:00 PM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.