EMERGENCY WATER OUTAGE
Feb 27, 2026 | 03:00 PM

EMERGENCY WATER OUTAGE
Feb 27, 2026 | 02:00 PM

DC Water Releases Key Findings on Extent of Sewer Overflow and Potomac River Impact

February 06, 2026
Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor located along the Clara Barton Parkway at the 495 interchange and C & O Canal National Historical Park. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates that approximately 243 million gallons of wastewater has overflowed from the collapse site. The vast majority of this volume, approximately 194 million gallons, occurred within the first five days, prior to the overflows being significantly reduced through bypass pumping operations.

Analysis of Potomac River flow data indicates that the estimated peak discharge of wastewater, approximately 40 million gallons per day, represents about 2% of the Potomac River’s total flow during that period.  

Ongoing water quality monitoring continues to show improving conditions downstream of the discharge point near Lock 10.   Since February 1, E. coli concentrations at all downstream sampling locations have remained within the US Environmental Protection Agency’s acceptable range for primary contact recreational activities, apart from a single day at Fletcher’s Boathouse.

Sampling within the drainage channel where the overflow occurred continues to show elevated E. coli levels. This is not unexpected, given intermittent residual discharges and snowmelt carrying remaining wastewater from the creek bed into the channel. Concentrations in this area are expected to fluctuate until residual material is fully flushed and baseline conditions are restored.

Efforts to reach the collapse site and finalize the repair strategy remain challenging due to the discovery of a rock dam inside the interceptor, which is significantly restricting internal access. DC Water is implementing a revised construction and repair approach that is expected to take 4-6 weeks and includes:

  • Construction of a new bypass pump location to enable the safe removal of rock at the collapse site.
  • Creation of a new upstream access point to facilitate repairs and enhance worker safety.
  • Development of a new downstream connection to the Potomac Interceptor to improve wastewater conveyance and reduce future risk.
  • Installation of an upstream bulkhead to restrict wastewater flow to the damaged section as much as possible.

In the interim, the existing bypass system remains operational and is successfully diverting wastewater around the damaged pipe section and back into the Potomac Interceptor. Some limited overflows have occurred, primarily due to increased wastewater flow associated with snowmelt and brief pump maintenance and operational issues. For example, during overnight pump maintenance, up to 300 gallons of wastewater escaped but was contained and did not reach the Potomac River.

Until full functionality is restored to the Potomac Interceptor, there remains a residual risk of additional limited overflows.  However, both the likelihood and volume of any future releases are expected to remain minimal.

DC Water continues to coordinate with federal, state and local partners, including Maryland Department of the Environment, DC Department of Energy and Environment, U.S. Environmental Protection Agency, public health officials, and other stakeholders. This coordination includes daily reporting, environmental impact evaluation, and development of remediation measures as appropriate.

Below are the latest results of water quality samples, utilizing a contracted environmental firm and certified laboratory, DC Water initiated daily sampling for E. coli, an indicator bacterium, at six (6) locations beginning on Jan 29, 2026. To assess water quality conditions, sampling locations including the overflow area as well as upstream and downstream sites.  The locations are shown on the following map, and the results are provided in the table below.

Water Quality Sampling Locations

map of sampling sites

Water Quality Sampling Results

chart of water quality test results

Consistent with public health and U.S. Environmental Protection Agency standards, E. coli levels below 410 MPN/100 mL are considered acceptable for primary contact recreational activity.

Historical data indicate typical levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges. 

Latest News

Graphic with meeting information

DC Water is inviting Maryland residents to join us tonight for a community meeting at Walt Whitman High School at 7 p.m. for an update about ongoing repair efforts on a section of the Potomac Interceptor sewer line that failed, directly impacting the surrounding Montgomery County communities. The meeting will provide an opportunity for residents to ask questions, learn about planned environmental restoration efforts, and next steps in the emergency repair and long-term rehabilitation efforts.

Placeholder DC Water Image

Crews continue work to clean the remaining debris upstream and downstream of the damaged Potomac Interceptor Pipe, with no overflows entering the Potomac River in 18 days.
A rock and debris dam that had been blocking the pipe has been removed, but some large rocks and boulders remain in other sections of the pipe and may require additional excavation to remove.

Photo of remaining rocks and debris

DC Water has made significant progress toward repairing a damaged section of the Potomac Interceptor. Crews are nearly done removing a rock and debris dam that was blocking the pipe. Several feet of rocks and debris remain to be cleared and is expected to be completed overnight. Ongoing work continues to maintain bypass pumping operations 24/7 with no overflows reported for 17 days.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.