DC Water Identifies Significant Rock Blockage in Potomac Interceptor, Impacting Cleaning and Repair Timeline

February 05, 2026
Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure. The unexpected discovery exposed the severity of the obstruction and prompted an immediate reassessment that will extend the timeline for cleaning and repairs.

It’s expected to take an estimated 4-6 weeks of additional time to get a system in place that will add more, larger bypass pumps in a new location and stabilize the site for heavy machinery to safely begin removing the large rocks and boulders inside the sewer line. While the existing bypass system has mostly contained overflows, more pumps are needed to further reduce the remaining flow getting through the pipe. A bulkhead will then be installed upstream of the failure to block the pipe and limit the wastewater reaching the collapse site.

A section of the sewer line collapsed January 19, along Clara Barton Parkway and the 495 interchange and the C & O Canal National Historical Park, causing an estimated 40 million gallons a day of wastewater to escape and enter the Potomac River.

Standard cleaning methods using industrial vacuums and jets are not sufficient to remove these large boulders. Addressing this blockage will require both larger machinery and manual labor. Workers will need to safely enter the pipe, use slings to maneuver around the rocks, and then rely on heavy equipment to extract each boulder, making removal a complex and highly specialized operation.

The large rocks blocking the pipe were likely excavated during original construction in the 1960’s and used as backfill. When the failure occurred, this material collapsed into the interceptor drawn in by the force of wastewater flow, eventually accumulating and creating this rock dam. Additional rock and soil entered the pipe as surrounding material eroded into the sinkhole created by the collapse.

To facilitate this work, DC Water will construct a new large pit upstream of the collapse to access the existing sewer line and install new, high-capacity pumps. Five more pumps—coming from Florida and Texas—will increase the pumps on site to 13 and increase capacity to more than 100 million gallons per day, allowing us to temporarily divert wastewater and keep the site as dry as possible for safe rock removal.

While the risk of limited overflows remains during this period, our teams are working around the clock to minimize impacts as much as possible. DC Water continues working with federal, state, and local regulators to evaluate the environmental impact and develop remediation plans. As part of this, DC Water is performing water quality sampling at several locations.

DC Water Bacteria Sampling after Potomac Interceptor Break

Utilizing a contracted environmental firm and certified laboratory, DC Water initiated daily sampling for E. Coli, an indicator bacterium, at six (6) locations beginning on Jan 29, 2026. To assess water quality conditions, sampling locations including the overflow area as well as upstream and downstream sites.  The locations are shown on the following map, and the results are provided in the table below.

Overall, results show mostly decreasing trends since the start of sampling.  Results at these sites, particularly the elevated concentrations observed at the overflow site in recent days, are expected as a result of limited overflow events that occurred. These are likely influenced by ice and snowmelt, which may increase system flows, contributing to overflow events during this emergency repair. Although the overflow is now mostly contained, E. coli levels are expected to continue fluctuating over time due to residual impacts from the incident and ongoing influences from weather conditions such as precipitation, snowmelt, temperature variability, and other natural sources of E. coli bacteria such as wildlife.

DC Water’s E. Coli Sampling Locations

Map of six testing locations. Old Angler's Inn, Drainage Channel Near Lock 10, Fletcher's Boathouse, Georgetown, Anacostia River South Capital St and National Harbor

Water Quality in the Potomac River

Chart of water Quality Sample Data
Note: MPN is most probable number

 

Consistent with public health and U.S. Environmental Protection Agency standards, E. coli levels which exceed 410 MPN/100 mL are considered unsafe.

Historical data indicate typical levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges. 

Latest News

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Pennyfield Lock Potomac Interceptor bypass pipeline running next to C & O Canal with equipment

There is no active spill or overflow. Work to strengthen the pipe to begin soon.

Today, DC Water completed construction on a temporary bypass system as part of sewer repairs on the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews turned on the pumps and successfully tested the system. With the bypass now ready, it will allow us to begin the emergency repairs inside the pipe by carrying the wastewater around the repair area.

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 23, 2026
Thursday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.