Sewer Repairs at 14th and F Nearing Completion; Road Closures Still in Effect

May 28, 2013

DC Water and contractor crews remain on the scene at 14th and F Streets, NW where they have completed repairs to a 54-inch diameter brick combined sewer line, and connections to storm basins on both sides of 14th Street. Today workers are completing a final joint repair on a 10-inch sanitary sewer. DC Water will then backfill the excavation in sequence to ensure the safety of the utilities above. The last steps include work by PEPCO and telecommunications utilities, then repair and restoration of the intersection.

Repairs have been complex and made more difficult due to a number of utilities and old trolley tracks located across 14th Street. DC Water repaired the brick sewer by installing a steel sewer liner. The large size of the sewer called for a nationwide search for parts. The steel pipe was trucked overnight to the District from Richmond, Virginia. Openings for the laterals that feed into the sewer pipe had to be individually cut and welded. In addition, a manhole for entry from the street, identified on DC Water records, was not readily accessible. It was eventually located eight feet below the surface of the road, paved over many times through the years.

DC Water and contractor crews have worked 24 hours a day during the repair work.

DDOT is managing traffic control during the process and traffic advisories can be found at www.ddot.dc.gov on the Featured News Section. The intersection remains closed to vehicular traffic at this time with the exception of two southbound lanes on 14th Street. Work began here last week and restoration of the street is expected by Friday, May 31.

Latest News

Photo of Potomac River at the overflow location

Hundreds of Sampling Results Confirm Return to Normal Bacteria Levels in Potomac River

DC Water has outlined its next steps to complete the environmental cleanup and its plan for continued water quality monitoring this summer, as part of the ongoing response to January’s failure in the Potomac Interceptor sewer pipeline. The plan, submitted to the Maryland Department of the Environment (MDE), is supported by extensive data from hundreds of samples.

crews removing soil in C & O Canal

Work continues to remove the remaining soil between locks 10 and 12 of the C & O Canal which was used as an emergency bypass while the Potomac Interceptor was repaired. Crews area also removing plants, trees, and shrubs in preparation for the long-term rehabilitation of the Potomac Interceptor.

Placeholder DC Water Image

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences, erosion and sediment controls, utilities, and ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Placeholder DC Water Image
Piney Branch Parkway Temporary Closure and Relocation

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

May 16
2:00 pm - 6:00 pm
May 20

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.