Potomac River Tunnel Project Mobilizes Construction Site at Capital Crescent Trail

March 06, 2025
Capital Crescent Trail trailhead – Water St, NW

This notice provides important information about mobilizing the Potomac River Tunnel (PRT) construction site at the Capital Crescent Trail in Georgetown.  Beginning on or about the week of March 10, 2025, DC Water’s contractors will start setting the site up for the first construction phase. The site is located along the bank of the Potomac River, near the trailhead of the Georgetown Capital Crescent Trail. DC Water will construct a diversion facility that will include a diversion chamber, an approach channel, a drop shaft, and other structures to convey flow from this location, to the tunnel, and an overflow structure. Initial site setup activities will involve installing fences and signage, clearing the site area, and setting up operations. 

Map of the diversion facility and overflow structure that DC Water will construct at the Capital Cresent Trail construction site.

 

 

Throughout construction, the Capital Crescent Trail will remain accessible to all users. However, multiple phases of trail shifts will be in place to direct trail users around the work zones. Advance notice of changes will be provided. Please send your email address to dcpotomacrivertunnel@dcwater.com if you would like to receive updates.  Thank you for your patience and cooperation as we work to complete this major infrastructure improvement project.

Site Mobilization – Capital Crescent Trail trailhead – Water St, NW  

During the Capital Crescent Trail site mobilization initial phase, the contractor will establish a safe and efficient work zone. Work includes placing signs along the Capital Crescent Trail and Water Street NW and flaggers directing traffic during working hours. The primary work area will be on the west side of the aqueduct and enclosed by fencing. The current traffic pattern under the aqueduct will remain for approximately two to three weeks.

Map: DC Water’s contractor will setup two work zones west of the aqueduct. The current traffic pattern under the aqueduct for trail users will remain the same for approximately two weeks. Flaggers will assist motorists visiting the Washington Canoe Club. 

Additional site preparations will include setting up chain-link fences around work zones, installing erosion controls, removing trees, and placing protections around remaining trees.  The contractor will grade the site and set up equipment and facilities to support the next stages of construction. The site will be restored at the end of the project. 

Construction Activities During Mobilization
The contractor will construct the following during mobilization. 

  • A new trail on the west side of the aqueduct to direct trail users around the construction site area.
  • A path on the north side of Water Street to direct pedestrians and bicyclists under the aqueduct.
  • Two lanes under the aqueduct: one for trail users and the Washington Canoe Club and another for accessing the construction site. 

Traffic Pattern Changes and Pedestrian and Bicycle Detours

  • Pedestrians and bicyclists will be detoured around work zones. Please follow the detour signs.
  • Parking restrictions on the south side of Water Street NW in front of the Potomac Boat Club.

Construction hours are 7:00 am – 7:00 pm, Monday through Friday. Temporary, short-term detours may occur periodically; road signs and/or flagging personnel will direct you around the work site. You may notice noise associated with construction during this phase. The contractor will install noise and vibration instruments to monitor construction noise.

Link: Capital Crescent Trail Construction Site Fact Sheet

What is the Potomac River Tunnel Project?
 

Map of the Potomac River Tunnel and the construction site locations.

The Potomac River Tunnel is the next major phase of the DC Clean Rivers Project. The project consists of constructing a large-diameter deep sewer tunnel, diversion facilities, drop shafts, and support structures to capture potential combined overflows of sewage and stormwater from existing locations along the Potomac River and convey them to the Blue Plains Advanced Wastewater Treatment Plant. The project is required to reduce wastewater overflows that contribute to water quality impairment of the Potomac River and ultimately Chesapeake Bay; and to comply with the 2005 Federal Consent Decree entered by DC Water, the District of Columbia, the US Environmental Protection Agency, and the US Department of Justice, as amended in January 2016. 

During large rain events, untreated stormwater and wastewater are released into the Potomac River when the system's capacity is exceeded. These overflows impair water quality by increasing water bacteria levels, contributing to low dissolved oxygen impacting aquatic life, and increasing the amount of trash in waterways.  An estimated 654 million gallons of combined stormwater and sewage overflows into the Potomac River in a year of average rainfall. The proposed controls are estimated to reduce the volume released to the Potomac River by 93% and reduce their frequency from approximately 74 events to 4 events in a year of average rainfall. 

Additional Information  

  • The work at this site will commence on or about the week of March 10, 2025. Workdays are Monday-Friday. Work hours are 7:00 AM – 7:00 PM. Work is expected through early 2030.
  • Commuters, pedestrians, and cyclists will notice additional construction equipment, personnel, and noise associated with construction activities.
  • Commuters and pedestrians will notice road signs and/or flagging personnel directing them safely around the work site.
  • Signage and project information signage will be posted throughout the project site.
  • The site layout and impacts will change as the work progresses. Updates will be provided in additional notices.
  • The site will be fully restored once construction is complete. 

For more information 
Project Email: dcpotomacrivertunnel@dcwater.com 
Project Website: www.dcwater.com/prt 
Dedicated Project Hotline: 202-972-1388 
DC Water 24-hour Emergency: 202-612-3400 

Stay in the loop! Get the latest project updates — email us at dcpotomacrivertunnel@dcwater.com to join our mailing list! 

Latest News

Close-up of the TBM cutterhead suspended by a crane

DC Water’s Newest Tunnel Boring Machine to Dig Tunnel’s Southern Segment

Emily, DC Water’s second tunnel boring machine for the Potomac River Tunnel Project, has arrived at the West Potomac Park construction site. Once assembled and launched, she will excavate the tunnel’s southern section.

Information for the DC Water Town Hall on a graphic

DC Water is reminding community members that it will host a Town Hall on Thursday, May 28, from 7–9 p.m. at DC Water Headquarters to discuss proposed Fiscal Year 2027 budget updates and rate ...

Graphic with information about the town hall

DC Water’s proposed $1.9 billion operating and capital budget for Fiscal Year 2027, focused on Smart Spending for a Resilient Tomorrow, includes funding to help provide safe, reliable drinking water, upgrade aging water and sewer infrastructure, reduce pollution in local waterways, and continue removing lead service lines across the District.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Close-up of the TBM cutterhead suspended by a crane
From Germany to DC, Emily Arrives on a One-Way Ticket to Help Build the Potomac River Tunnel

DC Water’s Newest Tunnel Boring Machine to Dig Tunnel’s Southern Segment

Emily, DC Water’s second tunnel boring machine for the Potomac River Tunnel Project, has arrived at the West Potomac Park construction site. Once assembled and launched, she will excavate the tunnel’s southern section.

Latest Blog Post
DC Water General Manager and CEO David Gadis recognizes Lily MacDonald during the May Board of Directors meeting.
From Classroom to Community: A Student Spotlight on DC Water's SPLASH Program
A speechwriting assignment became a call to action for water access and affordability through DC Water's SPLASH program.
Upcoming Meeting
Date
May 28, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.