EMERGENCY WATER OUTAGE
Feb 07, 2026 | 11:00 PM

Emergency Water Outage
Feb 07, 2026 | 04:00 PM

Emergency Water Outage
Feb 07, 2026 | 03:00 PM

NORTHEAST BOUNDARY SEWER MAIN EMERGENCY REPAIR AND MAINTENANCE PROJECT- 18TH & D STREETS NE AND 19TH & C STREETS NE

February 11, 2015

DC Water has found a significant structural fracture in its 23 foot high trunk, brick sewer main located near 18th Street and D Street NE. Following a thorough investigation of the sewer, it has been determined that there is a need to perform repairs and maintenance procedures to this portion of the sewer immediately. These procedures will require the inspection and cleaning of the sewer while examining the main and repairing structural damage. The project will include entering manholes in the streets to install safety equipment within the main, rehabilitating and strengthening the existing sewer main, and making the necessary repairs to this portion of the sewer main.

Benefits of this project include the rehabilitation of an aging sewer system, improving structural integrity while maintaining adequate hydraulic capacity, reducing stream and groundwater infiltration and potential sewer overflows. In preparation for this project, field investigations and evaluations are being conducted to assess the condition of the sewer.

SCOPE OF WORK
This project involves the internal repairs of approximately 100 linear feet of brick sewer main by utilizing the no-dig trenchless technology, and cleaning and lining of the sewer main.
SCHEDULE
•Construction Start: Week beginning February 9, 2015
•Estimated Construction Completion: Week ending March 27, 2015
•Normal work hours: 7:00AM – 7:00PM, Monday through Saturday
•Contractor may work on Sundays if additional construction activities are needed, or due to inclement weather.

IMPORTANT INFORMATION
•During the repair and maintenance of this sewer main, there will be varying lane closures and parking restrictions between 19th Street NE and 18th Street NE and between C Street NE and D Street NE. Additionally, there will be closure of the alley on 18th Street NE north of D Street NE.
•Traffic control, signage, security fencing and flagmen will be set up to maintain public safety during these construction operations.
•During sewer repair and maintenance procedures, you may experience excessive noise for abbreviated periods. DC Water will employ noise reduction equipment and methods to reduce noise impacts to the extent possible.
•DC Water will work to ensure minimal disruptions during construction operations and will restore all work sites to their original condition.

TRAFFIC PLANS
•Flagging operations will be used daily during repairs to maintain traffic in the work zone. All Traffic Control Plans will be approved by the District Department of Transportation (DDOT).
•“No Parking” signs will be placed in certain areas in and around the work zone and will be posted 72 hours prior to construction.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.