Lady Bird Emerges!

July 23, 2015

DC Water’s celebrated tunnel boring machine (TBM), Lady Bird, has completed her mission, creating a four-and-a-half-mile-long tunnel that will be used to help improve the water quality in the Anacostia River. Lady Bird completed her dig earlier this month and today her cutterhead was extracted from a 100-foot-deep shaft near DC Water’s Main Pumping Station in Southeast Washington, DC.

Lady Bird began her journey two years ago, in July 2013, from a starting point at the Blue Plains Advanced Wastewater Treatment Plant. She tunneled along the Potomac River northward to Poplar Point and then crossed under the Anacostia River and continued west, finishing at a deep shaft along Tingey Street, SE. To prepare for her arrival, this shaft was filled with flowable fill concrete and water, to protect against changes in pressure as Lady Bird mined through the shaft wall. Crews then dug out the concrete to reveal the muck-brown machine – the bright blue, green and white paint she wore into the tunnel long since burnished away. A special heavy-duty crane was deployed to hoist the cutterhead – the elaborate steel face of the machine with built-in cutting and slicing tools—and the other pieces of the TBM that were too heavy for the cranes on site.

“This is a terrific milestone for DC Water’s Clean Rivers Project,” said DC Water CEO and General Manager George S. Hawkins. “We are fortunate that the tunneling went so smoothly, finishing on time and on budget, and I applaud our DC Water staff as well as Traylor Skanska Jay Dee and everyone else who took part in this successful dig.”

DC Water’s Clean Rivers Project will incorporate two methods to keep combined sewage and stormwater from overflowing into waterways, during heavy rains in the parts of the city with a combined sewer system. The first is to build underground tunnels that will hold combined sewage and stormwater until rain subsides, then convey it for treatment at Blue Plains. The second is to create green infrastructure to capture and infiltrate rain on-site before it can reach the combined sewer system.

Carlton Ray, Director of the DC Clean Rivers Project, added “Lady Bird performed as well as projected—having a one-day best mark of 150 feet. In her best week, she tunneled 631 feet. This TBM’s success means we are one step closer to a cleaner Anacostia River.”

Lady Bird dug the southernmost segment of the Anacostia River Tunnel. The next section will be mined by another TBM named Nannie, who is preparing to begin her tunnel at a site near RFK Stadium. The Northeast Boundary Tunnel is the longest portion of tunnel, and that contract has yet to be awarded. At the northern tip of the tunnel system is the First Street Tunnel, a relatively short tunnel that will be mined by Lucy, and is designed as a flood protection project for the Bloomingdale and LeDroit Park neighborhoods.

Lady Bird removed approximately 1.2 million tons of material that she mined. This was hauled away in nearly 72,000 truckloads over the last two years. She built the tunnel with 28,189 pre-cast concrete segments which made up 4,027 full rings.

The cost of tunnel boring machines is included in the contract for each tunnel segment; therefore, the TBMs are owned by the contractors for each tunnel portion. Lady Bird is the property of the contractor and can be extracted and used on another project. Lady Bird is being sold back to her German manufacturer, Herrenknecht.

For more information about the Clean Rivers Project please visit: dcwater.com/cleanrivers
More information about Lady Bird can be found at: dcwater.com/ladybird

Videos of Lady Bird and the Clean Rivers Project can be viewed at:
https://www.youtube.com/watch?v=J5oEqtpB1go
https://www.youtube.com/watch?v=se5YebfWfkw

Latest News

Photo of Potomac River at the overflow location

Hundreds of Sampling Results Confirm Return to Normal Bacteria Levels in Potomac River

DC Water has outlined its next steps to complete the environmental cleanup and its plan for continued water quality monitoring this summer, as part of the ongoing response to January’s failure in the Potomac Interceptor sewer pipeline. The plan, submitted to the Maryland Department of the Environment (MDE), is supported by extensive data from hundreds of samples.

crews removing soil in C & O Canal

Work continues to remove the remaining soil between locks 10 and 12 of the C & O Canal which was used as an emergency bypass while the Potomac Interceptor was repaired. Crews area also removing plants, trees, and shrubs in preparation for the long-term rehabilitation of the Potomac Interceptor.

Placeholder DC Water Image

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences, erosion and sediment controls, utilities, and ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Placeholder DC Water Image
Piney Branch Parkway Temporary Closure and Relocation

DC Water has nearly completed construction site preparation for the Piney Branch Tunnel project, including tree removal, and installation of fences

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

May 16
2:00 pm - 6:00 pm
May 20

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.