Updated Maps: Independence Avenue, SW, Temporary Lane and Sidewalk Closures

July 24, 2024
Hydro excavating utilities with a vac truck.

(Washington, DC) – DC Water's Potomac River Tunnel Project contractor began utility tie-in operations along Independence Avenue, SW between Ohio Drive, SW, and West Basin Drive, SW on June 16, 2024. This work requires phased temporary closures of one to two eastbound travel lanes and one to two westbound travel lanes on Independence Avenue the crosswalk at West Basin Drive and Independence Avenue and the sidewalk on the south side of Independence Avenue (adjacent to West Potomac Park). Work hours are Monday through Friday from 7:00 pm to 5:30 am for the two-lane closures and from 9:30 am to 2:30 pm for the single-lane closures, weather permitting. All travel lanes reopen during non-working hours. Please refer to Maps A, B, and C below for additional details.

The tie-in work is necessary to construct a relocated Ohio Drive and to prepare the site for the Potomac River Tunnel (PRT) Project. The contractor will restore the work areas when the tie-in work is completed. 

Independence Avenue, SW Work (Maps A, B, & C)

  • Date: June 16 – October 6, 2024
  • Time: Monday – Friday, from 7:00 pm – 5:30 am for two-lane closures; Monday – Friday, from 9:30 am – 2:30 pm for single-lane closures.
  • Location: Independence Avenue, SW between Ohio Drive, SW and West Basin Drive, SW
  • Traffic Patterns and Pedestrian Detours: 
    • Traffic: Temporary eastbound and westbound lane closures on Independence Avenue between Ohio Drive and West Basin Drive. See Maps A and B for additional details.
    • Pedestrian Detours: Temporary sidewalk and crosswalk closures adjacent to West Potomac Park along Independence Avenue between Ohio Drive and West Basin Drive. See Map C for additional details.

Independence Ave one lane closure

Map A: (Independence Ave, SW) One Lane Closure Configuration

 

Independence Ave two lane closures

Map B: (Independence Ave, SW) Two Lane Closure Configuration

 

Independence Ave pedestrian detour

Map C: (Independence Ave, SW) Pedestrian Detour

Important Information

  • The sidewalk and crosswalk identified on the maps above will remain closed for the duration of the tie-in work. 
  • Motorists and pedestrians will notice road signs and flagging personnel directing them around the work zones. 
  • Please plan your travel routes accordingly and anticipate potential delays. Traffic control measures will be in place to guide motorists safely through the area.
  • Alternative pedestrian routes will be provided, and signage will be posted to direct pedestrians to safe pathways. Refer to Map C for the detour route. 

Project Details

The Potomac River Tunnel is the next major phase of the DC Clean Rivers Project. The project consists of a large-diameter deep sewer tunnel, diversion facilities, drop shafts, and support structures to capture flows from existing combined sewer overflows (CSOs) along the Potomac River and convey them to the Blue Plains Advanced Wastewater Treatment Plant. The project is needed to reduce CSOs that contribute to water quality impairment of the Potomac River and ultimately the Chesapeake Bay; and to comply with the 2005 Federal Consent Decree entered by DC Water, the District of Columbia, the US Environmental Protection Agency, and the US Department of Justice, as amended in January 2016.

CSOs are released into the Potomac River from CSO Outfalls during rainfalls that exceed the system capacity. CSOs impair water quality by increasing water bacteria levels, contributing to low dissolved oxygen impacting aquatic life, and increasing the amount of trash in waterways. An estimated 654 million gallons of CSOs currently enter the Potomac River in a year of average rainfall. The proposed controls are estimated to reduce the volume of CSOs to the Potomac River by 93% and reduce their frequency from approximately 74 events to 4 events in a year of average rainfall.

For more information 

Project Email: dcpotomacrivertunnel@dcwater.com
Dedicated Project Hotline: 202-972-1388
Project Website: www.dcwater.com/prt 
DC Water 24-hour Emergency: 202-612-3400

Latest News

Photo of extended excavation site with trench boxes

The excavation around a damaged section of the Potomac Interceptor has been extended and trench boxes installed to provide shoring and stability. This doubles the size of the excavated area, to connect the collapse site with a downstream access point to the Potomac Interceptor.

CEO David L. Gadis with HSEMA, EPA and USACE

DC Water crews are working around the clock to keep the Potomac Interceptor repair site safe as another storm approaches. Since February 8, there have been no overflows to the Potomac River, and efforts are underway to bolster pump capacity and manage stormwater runoff due to expected heavy rain and snow that could flood the pumping site and endanger pumping operations.

Graphic with details about the two community meetings.

DC Water will host two community meetings to provide a comprehensive update on the Potomac Interceptor response, current system status, and next steps in emergency repair and long-term rehabilitation ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 26, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.