EMERGENCY WATER OUTAGE
Mar 24, 2026 | 07:00 PM

EMERGENCY WATER OUTAGE
Mar 24, 2026 | 02:30 PM

Heavy Construction for First Street Tunnel Project is Underway- Commuters/Through Traffic Travelers are Advised to Seek Alternative Routes

September 09, 2014

(Washington, DC) – DC Water is performing construction activities in four surface locations in the Bloomingdale neighborhood as part of its First Street Tunnel Project.

This important local flood control and environmental project will be under construction until March 2016, and traffic impacts will be 24 hours, 7 days per week for the duration of the project.

Surface Locations and Related Traffic Impacts
Adams Street NW, from First Street NW through the intersection with Flagler Place NW
• Construction is in progress. This portion of Adams Street will be closed to through traffic beginning the week of Monday, August 25, 2014 until February 2016. Adams Street will be open to local traffic only from First Street and 2nd Street.

V Street NW, through the intersection with First Street NW
• Construction is in progress. Beginning on or about Wednesday, September 10, 2014 until November 2014, First Street will be closed to through traffic at the intersection with V Street to allow for the construction of a diversion chamber in the center of the roadway. This portion of First Street will be open to local traffic only from U Street and W Street. An extended closure at this location may be required, and public notification will be provided.

Thomas Street NW at First Street NW
• Construction is in progress. Beginning the week of Monday, August 25, 2014 until September 2015, the 100 Block of Thomas Street and adjacent privately owned parking lot will be closed to through traffic to allow for the construction of a temporary pump station and associated structures. Thomas Street will be open to local traffic only from 2nd Street.

First Street NW, between Channing Street NW and Michigan Avenue NW
• Construction at the main mining shaft site is underway. Work will continue at the McMillan Sand Filtration Site until March 2016. First Street will remain closed to northbound/southbound traffic through November 2014. It is advised that North Capitol Street be used as an alternative route for travel on First Street.

Other Important Information
* Temporary traffic signs will be set up throughout the area to alert motorists to the traffic changes.
* Some traffic delays within the vicinity of the work zones should be anticipated.
* Sidewalk detours have been implemented to assist pedestrians.
* Noise, vibration and dust levels are all closely monitored and will continue for the duration of the project.

Project Details
The First Street Tunnel Project extends along First Street NW, beginning at the McMillan Sand Filtration Site below ground, and heading southbound to Rhode Island Avenue NW. The First Street Tunnel was accelerated as part of the Mayor’s Task Force on the Prevention of Flooding in Bloomingdale and LeDroit Park to relieve street and basement flooding in these neighborhoods. DC Water has hired the Design-Build firm of Skanska-Jay-Dee to construct the tunnel and associated structures.
###

About DC Water
The District of Columbia Water and Sewer Authority (DC Water), is an industry leading multi-jurisdictional regional utility that provides drinking water, wastewater collection and treatment to 600,000 residential, commercial and governmental customers in the District of Columbia, 17.8 million annual visitors and also collects and treats wastewater for 1.6 million customers in Montgomery and Prince Georges counties in Maryland and Fairfax and Loudoun counties in Virginia.

DC Water’s service area covers approximately 725 square miles and the company operates the world’s largest advanced wastewater treatment plant with a capacity of 370 million gallons per day and a peak capacity of 1.076 billion gallons per day.

Please visit dcwater.com/firststreettunnel for more information on the First Street Tunnel Project.

Latest News

Placeholder DC Water Image

DC Water has completed sludge removal on a section of the C & O Canal between locks 13 and 14, which was used as a bypass to divert wastewater around the collapsed section of the Potomac Interceptor and back into the pipe further downstream. Crews are now constructing an access bridge to this section of the canal to allow soil removal to begin.

Overhead Photo of Potomac Interceptor

Comprehensive Survey to Guide Rehabilitation and Address Changing Site Conditions

Starting later this week, DC Water will conduct an aerial drone assessment along the 54-mile Potomac Interceptor (PI) to evaluate current site conditions and better understand the changing landscape and development along the Potomac Interceptor alignment, including areas where there may be rocks or boulders that need further on the ground inspections.

Photo of someone using the tap water with the dates of the annual water line cleaning March 23 - May 4

Spring cleaning isn’t just for closets and cabinets. DC Water’s system gets a refresh too!

Starting March 23, DC Water will begin work that helps maintain more than 1,300 miles of water lines across the District. During this time, the disinfectant used in drinking water will temporarily switch from chloramine to chlorine through May 4. This switch helps support overall water quality throughout the year.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.