First Street Tunnel winter construction is key step before commissioning Northeast Boundary Tunnel

December 12, 2022

WASHINGTON, DC — DC Water will reach a significant milestone for the Clean Rivers Project when it places the Northeast Boundary Tunnel (NEBT) into operation during the summer of 2023. The NEBT will increase the combined storm runoff capacity of the Anacostia River Tunnel (ART) system as it directs captured flows of combined stormwater and sewage to the Blue Plains Advanced Wastewater Treatment Plant for treatment. This will significantly reduce flooding events in the Bloomingdale and LeDroit Park neighborhoods.

To achieve this milestone next year, DC Water will begin the next phase of construction by temporarily taking the First Street Tunnel (FST) out of service from December 2022 through February 2023.

“The work this winter is a critical preparatory step to make the final connection between the Northeast Boundary and First Street tunnels next year,” said Moussa Wone, Director of DC Water’s Clean Rivers Project. “Once that link is established and the NEBT is in service, there will be a continuous 13-mile- long, 100-foot-deep tunnel, with 190 million gallons of  storage, from Bloomingdale to Blue Plains.”

Workers will isolate the tunnel from the existing sewer system, clean the tunnel and remove a concrete structure that currently directs flow to the temporary pumping station at Thomas Street, NW. The entire procedure is expected to take about three months to complete.

DC Water scheduled the work to take place during the winter season when serious storms are least likely to occur. The FST is a key component for flooding mitigation in and around the Bloomingdale and LeDroit Park neighborhoods.

DC Water’s Clean Rivers team has developed measures to mitigate the impact of taking the tunnel out of service. These measures—and the project itself—have been the subject of numerous DC Water meetings with ANCs, community groups, tunnel forums, and key stakeholders.

Facilities that will remain in service during the FST shutdown are Irving Street’s green infrastructure, the McMillan Stormwater Storage Facility, the stormwater sewer pipe under Rhode Island Ave NW, and pervious pavement (that absorbs rainwater) installed in Bloomingdale neighborhood alleys.

To mitigate flooding through this construction:

DC Water will:

  • Clean catch basins in the Bloomingdale area at least once a month
  • Prepare sandbags and make them available in the neighborhood if a major event is predicted. This is specific to the areas that the First Street Tunnel serves. Contact DC Water’s 24-hour Command Center at 202-612-3400.
  • If during the construction, a large storm is forecast, DC Water can put the FST back into service with 24 hours advance notice 

Residents in the affected areas should:

  • Consider adding a backflow prevention device if they have not already (DC Water has a discount/reimbursement program for impacted residents in these neighborhoods.)
  • Look into DC Water’s Floodproofing Rebate Program for residents of Bloomingdale and LeDroit Park
  • Sign up to receive e-newsletters about the project, by sending your email address to dcclearrivers@dcwater.com
  • Visit the project website at dcwater.com/NEBT for more information
  • E-mail questions to DCCleanRivers@dcwater.com or call the 24/7 NEBT Hotline at 800-988-6151
  • For emergencies, contact DC Water’s 24-hour Command Center at 202-612-3400

Channing Street residents may notice increased activity, equipment staging, vehicular traffic, and construction work in their area.

DC Water continues to work with the community during this important project to improve the Anacostia River and mitigate flooding.

More information on the complete program can be found at: dcwater.com/cleanrivers

Latest News

Photo of soil removal and excavation

DC Water and its contractor have removed all the soil down to the clay liner between locks 12 and 13, marking 50% completion of the canal clean-up. Soil removal between Locks 13 and 14 was completed earlier this month. Meanwhile, clean-up efforts continue between locks 10 and 12, with sludge removal complete and soil removal now underway.

View of Mary at bottom of shaft inside tunnel shown from above

First turn of cutterhead signals the start of excavation for the Potomac River Tunnel Project

In a defining moment for one of the District’s largest infrastructure investments, DC Water has marked its next major milestone in the Potomac River Tunnel Project. The first tunnel boring machine, Mary, has launched her northbound journey breaking through the soil to signal the start of excavation.

With the first turn of Mary’s drill-like cutterhead underground, the machine pushed forward to begin tunneling, representing the transition from years of planning and preparation to active tunnel construction on the $819 million project.

Photo of the vegetation growing back in the culvert area
  • DC Water has completed soil removal, utilizing excavators and manual digging, to expose the clay lining for the C & O Canal between locks 13 and 14. This is the final step in the clean-up process ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

View of Mary at bottom of shaft inside tunnel shown from above
DC Water Launches Tunnel Boring Machine Mary, Marking Important Step for Potomac River Tunnel Project

First turn of cutterhead signals the start of excavation for the Potomac River Tunnel Project

In a defining moment for one of the District’s largest infrastructure investments, DC Water has marked its next major milestone in the Potomac River Tunnel Project. The first tunnel boring machine, Mary, has launched her northbound journey breaking through the soil to signal the start of excavation.

With the first turn of Mary’s drill-like cutterhead underground, the machine pushed forward to begin tunneling, representing the transition from years of planning and preparation to active tunnel construction on the $819 million project.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 15, 2026
Wednesday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.