DC Water’s tunnel boring machine Lucy makes it home for the holidays

December 22, 2015

If you thought holiday traffic was bad, consider this—it took DC Water’s tunnel boring machine named Lucy five months to travel 2,700 feet. Granted, she did it about 100 feet below ground and had to cut her way through 500 million pounds of sand, silt and clay. Lucy mined under First Street, NW, from Channing Street to Rhode Island Avenue, to create the First Street Tunnel. This tunnel segment will ultimately connect to the five-mile-long Northeast Boundary Tunnel in 2022.

“We are pleased to reach this important milestone in the project and are grateful for the continued patience of the impacted community,” said DC Water CEO and General Manager George Hawkins. “We will continue to work with the neighborhood to complete this essential project as soon as possible to provide flood relief for residents.”

From 2016 to 2022 the First Street Tunnel will store and then pump combined sewage up into the existing sewer system during and after rainstorms to keep it off of streets and out of basements. The First Street Tunnel is designed to mitigate flooding from undersized sewers in the Bloomingdale and LeDroit Park neighborhoods. It is part of the DC Clean Rivers Project aimed at significantly reducing combined sewer overflows to District waterways.

DC Water selected Skanska/Jay Dee Joint Venture for the project in 2013. Lucy was christened in a ceremony in April of this year and began her dig this summer. Scott Hoffman, Skanska/Jay Dee Project Manager for the First Street Tunnel said the joint venture team was committed to this project and the challenge of conducting heavy civil work in a densely populated urban area. “We’re proud of the end result, and the positive impact it will have on the community,” Hoffman said. “It’s a great accomplishment to have Lucy finish the tunneling portion of the work just in time for her to go home for the holidays.”

Lucy was named honoring Lucy Diggs Slowe (1895-1937), a District of Columbia local and the First Dean of Women at Howard University in 1922. There, she established a women’s campus and influenced the appointment of women’s deans throughout the country. Prior to that, Ms. Diggs Slowe founded – and served as principal for—Shaw Junior High School in 1919, the first junior high in the District of Columbia school system. She was a founding member of Alpha Kappa Alpha Sorority, Inc. and was inducted into the 26th annual Maryland Women’s Hall of Fame. In addition, she was a decorated athlete, winning the American Tennis Association’s first tournament in 1919, making her the first African-American woman to win a major sports title.

This is the second DC Water tunnel boring machine to complete her mission this year. In July, Lady Bird completed a two-year, 4.5 mile trek to dig the Blue Plains tunnel segment.

Now Lucy will be dismantled and 99 percent of her parts will be recycled, while the tunnel she dug is prepared for use. Work also continues to connect the existing sewers along First Street, NW to the new tunnel. For more information on the project, please visit: dcwater.com/firststreettunnel.

Latest News

Section of Potomac River in Cabin John, MD showing river and trees

Testing will continue through September 10 at six Maryland locations closest to January sewer collapse

DC Water is moving from daily Potomac River water quality testing to testing twice a week. The change is part of our continued response to the January Potomac Interceptor sewer collapse. Daily testing continued past the original July 31 end date and today will be the last day DC Water will test at the 10 current locations.

Map: Temporary southbound lane closure on Rock Creek and Potomac Parkway NW.

Starting on or about Aug. 7, 2026, weather permitting, drivers can expect a temporary lane closure southbound on Rock Creek and Potomac Parkway NW near the intersection of Virginia Avenue NW and F ...

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.