EMERGENCY WATER OUTAGE
Mar 24, 2026 | 07:00 PM

EMERGENCY WATER OUTAGE
Mar 24, 2026 | 02:30 PM

DC Water, Residents and Mayors Task Force Celebrate Progress in Bloomingdale/LeDroit Park

June 27, 2014

Today, DC Mayor Vincent C. Gray, City Administrator and Chairman of the DC Water Board of Directors Allen Y. Lew, and DC Water General Manager George S. Hawkins broke ground on the First Street Tunnel—a large, underground cistern that will store stormwater during intense rainstorms to mitigate flooding in Bloomingdale and LeDroit Park. Also today, the group celebrated two large measures already in operation in the neighborhoods that are providing some flooding relief.

The two neighborhoods are connected to an undersized sewer system and have been subject to flooding during heavy rains for more than a century. DC Waters long-term approach to this problem, the Clean Rivers Project, is a tunnel system for the District of Columbia that will add capacity to the sewers and is scheduled for completion in 2025.

All of the measures marked at todays event came from the Mayors Task Force Report on the Prevention of Flooding in Bloomingdale and LeDroit Park. Mayor Gray established the task force in August 2012 after four successive flooding events. Mayor Gray named Mr. Lew and General Manager Hawkins as co-chairs.

Commenting on todays celebration, Mayor Gray said, "I convened the Task Force to investigate whether we could put in place interim measures before DC Waters long-term solution (The Clean Rivers Project) is complete in the next decade. I applaud the Task Force and DC Water for their ingenuity, coordination and commitment to solving the flooding issues. The residents in these neighborhoods have seen improvement already, and long-term relief is on the way at a faster pace."

DC Water Chairman Lew said, "This is a problem that has persisted for more than a century, but Mayor Gray made it a priority and tasked us with finding solutions that could be implemented immediately to make these communities whole and greatly reduce the risk of flooding. Thats why we are here today to break ground on the First Street Tunnel nine years ahead of schedule."

DC Water General Manager Hawkins said, "Our team investigated more than 40 different engineering solutions and crafted a creative plan to address the flooding with incredible speed. The two measures in place have proven successful through the tests of this springs rains. These solutions by themselves do not solve the problem—we most likely will still have flooding in a severe storm—but the progress is apparent and we are well on our way to offering lasting relief."

First Street Tunnel
Todays groundbreaking is for the First Street Tunnel, a 20 1/2-foot diameter tunnel under First Street, NW. The Authority will construct this tunnel to hold eight million gallons of wastewater and stormwater during heavy rain events, using a temporary pumping station to carry flow into the Northeast Boundary sewer after the storm passes. Completion is projected for spring 2016.
McMillan Stormwater Storage
DC Water converted the former McMillan Sand Filtration Plant into storage for up to three million gallons of stormwater, using an existing underground basin. During large storm events, flow will be diverted from feeder sewers adjacent to the McMillan site, capturing stormwater before it reaches the sewer system. This will help reduce the excessive pressure that currently causes sewer backups and overland flooding during heavy rainstorms. Construction began in December 2012 and was completed earlier this year.
Irving Street Green Infrastructure
Nearing completion are more than a dozen bioretention areas along the Irving Street corridor just north of the Bloomingdale neighborhood. This green infrastructure will capture, infiltrate and treat stormwater runoff before it enters the sewer system, and provide other environmental and social benefits to the community.

Stormwater Improvements
In addition, last year, with funding from DC Water, the District Department of Transportation (DDOT) installed a new 60-inch stormwater pipe under the median in the 100 block of Rhode Island Avenue, NW – a project completed ahead of schedule. DDOT also enlarged catch basins to remove stormwater from neighborhood roadways; installed a rain garden at the intersection of T Street and Rhode Island Avenue, NW; and installed permeable pavement in a Bloomingdale alley.

Ultimately, DC Waters Clean Rivers Project will resolve the flooding issues in these neighborhoods. To ensure this, the Authoritys engineers planned a realignment and acceleration of the Northeast Boundary Tunnel portion of the project. The new alignment will create less disruption and involve less private property during construction than the prior plan. When this section of tunnel is complete, now scheduled in 2022, DC Water will convey the flow from the First Street tunnel to the Blue Plains Advanced Wastewater Treatment Plant.

Other steps for mitigating flooding since 2012 have included:
- A thorough visual inspection of sewers in these areas;
- A rebate program for installing backwater valves;
- Individual engineering consultations to address overland flooding issues;
- A rain barrel-subsidy and installation program

The Mayors Task Force on the Prevention of Flooding Final Report is available for download at: www.oca.dc.gov.

Latest News

Placeholder DC Water Image

DC Water has completed sludge removal on a section of the C & O Canal between locks 13 and 14, which was used as a bypass to divert wastewater around the collapsed section of the Potomac Interceptor and back into the pipe further downstream. Crews are now constructing an access bridge to this section of the canal to allow soil removal to begin.

Overhead Photo of Potomac Interceptor

Comprehensive Survey to Guide Rehabilitation and Address Changing Site Conditions

Starting later this week, DC Water will conduct an aerial drone assessment along the 54-mile Potomac Interceptor (PI) to evaluate current site conditions and better understand the changing landscape and development along the Potomac Interceptor alignment, including areas where there may be rocks or boulders that need further on the ground inspections.

Photo of someone using the tap water with the dates of the annual water line cleaning March 23 - May 4

Spring cleaning isn’t just for closets and cabinets. DC Water’s system gets a refresh too!

Starting March 23, DC Water will begin work that helps maintain more than 1,300 miles of water lines across the District. During this time, the disinfectant used in drinking water will temporarily switch from chloramine to chlorine through May 4. This switch helps support overall water quality throughout the year.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.