DC Water isolates leak in 3rd Street Tunnel, transitions to repair

August 24, 2021
3rd Street Tunnel

Water service restored to all customers on Monday;
DC Water partnering with District agencies on unified response

DC Water continues to address the water main break in the 3rd Street Tunnel. The break is on an 8-inch main that runs through the tunnel, though the exact location of the break is still being determined.

DC Water will provide an update on the time to repair once the location and repair needs are determined. The system pressure remains stable, and we do not anticipate any additional outages related to this incident. The tunnel closure is confined to the area of the break. Commuters can travel northbound as far as Massachusetts Ave, NW and southbound from Massachusetts Ave, NW.

DC Water CEO and General Manager David L. Gadis, commented, “The good news is that we were able to restore water service to all customers yesterday. All but one building were back in service by late afternoon and the remaining building, 307 K Street, NW, had water service in the evening. Still, DC Water mobilized bottled water distribution to 307 K Street NW and delivered nearly 650 cases of water to the building.”

Gadis added, “I would like to thank all the staff and agencies involved in this event. The District agencies and the Executive Office of the Mayor quickly coordinated and have provided a joint response. This is arduous work, around the clock, in extreme heat—all the responders have my gratitude.”

As there are many causes of water main breaks and leaks, DC Water will have a better understanding of the cause of the infrastructure failure in this case once the water main is exposed. A specific cause is not always determined.

Elsewhere in the District yesterday were reports of low water pressure in Northwest; however, those were related to hydrant flushing— the practice of opening fire hydrants to pull fresh water through the system— and were unrelated to this incident. That work was completed yesterday afternoon and DC Water confirmed that water pressure was restored to those customers.

 

Latest News

Photo of completed repair with concrete encasing the sewr pipe

DC Water has successfully completed emergency repairs on a critical section of the Anacostia Force Main following a failure near Anacostia Avenue and Ponds Street Northeast in July. With repairs finalized, attention now turns to rehabilitating other vulnerable segments of the 6.25-mile pipeline to ensure long-term reliability and resilience. 

Map of construction area on Clara Barton Parkway near I495

DC Water will be doing construction as part of a sanitary sewer rehabilitation project on Clara Barton Parkway in Maryland from Sept 8 - Oct 10, 2025, which may cause delays inbound near the I-495 Beltway interchange. One lane will be closed in the work zone to reline an 800-foot section of the sewer line, known as the Potomac Inteceptor. Access to the inner and outer loops of the Beltway will remain available.

Rock Creek Trail Site for Potomac River Tunnel Project

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Rock Creek Trail Site for Potomac River Tunnel Project
Ground Stabilization Work Begins Near Watergate Complex, starting Aug 25

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
September 18, 2025
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.