EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 05:30 AM

EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:30 AM

EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:00 AM

DC Water General Manager George Hawkins Testifies at House Hearing on U.S. EPAs Integrated Planning Framework

July 27, 2012

July 26, 2012 - DC Water General Manager George S. Hawkins testified Wednesday on behalf of the National Association of Clean Water Agencies (NACWA) at the U.S. House of Representatives Subcommittee on Water Resources and Environment hearing regarding U.S. EPAs final integrated planning framework. General Manager Hawkins is Chair of the NACWAs Money Matters Task Force, responsible for providing guidance on new approaches to Clean Water Act (CWA) affordability.

As the CWA celebrates 40 years, there is no doubt that compliance places an enormous financial burden on wastewater utilities. CWA obligations for combined sewer overflows, sanitary sewer overflows, and stormwater regulations as well as pollutant-based requirements such as nutrient limits and other total maximum daily loads and effluent limitations can cost utilities in the billions of dollars. U.S. EPAs integrated planning framework recognizes that allowing some flexibility and extending the timeframe for compliance would provide some relief to utilities, and therefore their ratepayers as well.

“We strongly believe that we can achieve water quality goals with fewer resources by using innovative approaches and addressing the most challenging problems first,” said Hawkins. “In addition, NACWA will be focused on making sure that all communities, not just those having faced or now facing enforcement actions, can use an integrated planning approach to meet their permit obligations.”

Hawkins also spoke to DC Waters case, commenting that improved flexibility and adaptability could help alleviate the massive burden placed upon DC Water and its ratepayers. Between the Clean Rivers Project to nearly eliminate combined sewer overflows and the Enhanced Nutrient Removal Facilities designed to reduce nitrogen loads to receiving waters, CWA mandates will cost roughly $3.5 billion.

Hawkins outlined the following four points regarding the U.S EPAs integrated framework:

1. NACWA urges Congress to provide initial financial support for the development of municipal plans in pilot communities across the country.

2. Congress should allow for NPDES permit terms to be extended up to 25 years for a community with an approved integrated plan to allow those communities some assurance and certainty that their clean water investments will be secure for longer than five years.

3. EPAs framework encourages the use of innovative, cost-saving tools such as green infrastructure and water quality trading as part of a communitys an integrated plan. These tools need time to develop and mature, and will not be considered viable options if only given a few years to employ.

4. NACWA has also long supported the creation of a dedicated source of funding for wastewater infrastructure investments to ensure that communities can meet their obligations under the Clean Water Act (CWA). A Clean Water Trust Fund, similar to those that finance highways and airports, would provide a federal contribution to supplement existing local and state revenue to help communities meet CWA unfunded mandates.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.