Emergency Water Outage
Feb 07, 2026 | 04:00 PM

Emergency Water Outage
Feb 07, 2026 | 03:00 PM

Emergency Water Outage
Feb 07, 2026 | 03:00 PM

DC Water brings drinking water quality improvements to the Bloomingdale neighborhood

November 04, 2016

This week, DC Water began work to replace old water mains in the Bloomingdale neighborhood in Northwest, DC. Some of the water mains in the neighborhood were installed in the late 1800s and are past their useful life. In fact, there have been about 25 water main breaks in the area since 2000, most of them occurring in just two blocks.
 
DC Water will replace close to a mile of 8-inch and 12-inch water mains. In addition to improving system reliability, the replacement program will also provide increased water pressure and unimpeded water flows. Within the same program, the Authority will also replace fire hydrants, valves and service lines located in public property. DC Water will replace any lead service lines in public space and will also offer to replace the private side (on homeowners’ private property) at the same time—at the homeowners’ expense, a cost-effective measure since the contractors will already be excavating in the neighborhood.
 
DC Water CEO and General Manager George S. Hawkins commented, “This program follows another DC Water project in Bloomingdale to bring even more improvements to the neighborhood. The first project created the First Street Tunnel to mitigate flooding and sewage back-ups during rainstorms in Bloomingdale and LeDroit Park, neighborhoods that are more than 100 years old – like much of the underground infrastructure that serves them.”
 
The project is scheduled for completion in late February 2017 with restoration of the area slated for spring 2017. Typical work hours are from 10:00 a.m. to 4:00 p.m. Monday through Friday, though there may be some night or weekend work. Residents will be notified in advance for work outside the stated schedule.
 
Residents can also expect water shut-offs while pipes are replaced (four to eight hours maximum), additional truck traffic, construction noise and parking restrictions. DC Water has made accommodations for additional parking areas. Any obstructions remaining from the First Street Tunnel Project will be removed.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.