EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 05:30 AM

EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:30 AM

EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:00 AM

DC WASA Hosts Industry Outreach Meeting on Combined Sewer Overflow Long Term Control Plan Tunnel Program

October 05, 2009

As part of its Combined Sewer Overflow Long Term Control Plan (LTCP), DC WASA will hold an Industry Outreach Meeting on Friday, October 30, 2009, at the Blue Plains Advanced Wastewater Treatment Plant to present project goals, the procurement process, and contract terms and conditions for the Blue Plains Tunnel design-build project.

In 2002, DC WASA prepared a Long Term Control Plan (LTCP) for the District’s combined sewer system to reduce Combined Sewer Overflows (CSOs) and comply with the Clean Water Act. The LTCP provides for the control of CSOs to the Anacostia and Potomac Rivers and Rock Creek in Washington, D.C. Following EPA approval of the LTCP, the United States, the District of Columbia, and DC WASA entered into a Consent Decree to implement the LTCP, which includes a series of underground storage and conveyance tunnels. The total project cost is projected to be $2.2 billion.

These tunnels will be approximately 23 feet in diameter and approximately 100 feet underground. By the year 2025, the fully constructed CSO program will reduce combined sewer overflows to local waterways by 96% overall, and by 98% in the Anacostia River alone.

The Blue Plains Tunnel will be the first of four major tunnel sections to be constructed. The tunnel will begin at DC WASAs Blue Plains Advanced Wastewater Treatment Plant, run north along the Potomac and Anacostia Rivers, cross under the Anacostia River at Poplar Point, and end at DC WASAs Main Sewage Pumping Station.

At 23,600 feet, the Blue Plains Tunnel is the largest of the contracts with an estimated construction value of $250 to $300 million.

In addition to presenting procurement and contract-related information, the meeting will be an opportunity for attendees to ask questions about the project. Following the Q&A, there will be time for networking with other firms in attendance.

The meeting will be held on Friday, October 30, 2009, from 10:00 am to 12:00 noon at DC WASA’s Central Operations Facility (on the Blue Plains Advanced Wastewater Treatment Plant site), 4th Floor, Room 409, 5000 Overlook Avenue SW, Washington, D.C. 20032.

To make reservations, call Ms. Melva Massey at (202) 787-2363 or send an email to mmassey@dcwasa.com. Reservations should be made no later than Wednesday, October 28, 2009. Space will be limited; therefore, firms attending are limited to attendance of two (2) persons. Reservations will be given preference should space become limited.

Persons attending will need to obtain a visitor’s pass at the security building located at the plant’s entrance. Please allow 30 to 45 minutes to complete this process. The Central Operations Facility (COF) building is located immediately to the right of the entrance gate. Parking will be available in designated areas around the building. For more information on the overall program, please reference the link below.

###
About The District of Columbia Water and Sewer Authority
The District of Columbia Water and Sewer Authority (WASA) is an industry-leading authority of District government that provides drinking water and wastewater collection and treatment for a population of more than 500,000 in the District of Columbia. DC WASA also treats wastewater for a population of 1.6 million in Montgomery and Prince Georges counties in Maryland, and Fairfax and Loudoun counties in Virginia. The Authority operates the world’s largest advanced wastewater treatment plant, with a capacity of 370 million gallons per day and a peak daily capacity of more than a billion gallons. DC WASA’s service area covers approximately 725 square miles.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.