EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:30 AM

EMERGENCY WATER MAIN REPAIR
Feb 08, 2026 | 04:00 AM

EMERGENCY WATER OUTAGE
Feb 08, 2026 | 01:00 AM

Clean Rivers Project Construction on Rhode Island Avenue Begins February 22

February 21, 2013

(Washington, DC) – DC Water will be performing construction activities on and adjacent to Rhode Island Avenue as part of the Clean Rivers Project.

Beginning Friday, February 22, 2013 through July 2013, weather permitting, crews will be working in seventeen locations from 6th Street, NW to the Rhode Island Avenue Metro Station.

This work will be performed in support of the Northeast Boundary Tunnel portion of the Clean Rivers Project. In preparation for future tunnel construction, crews will be drilling at several locations as part of needed field investigations.

Daily hours of operation on Rhode Island Avenue at First Street, NW and Lincoln Road, NE will be from 9:00 a.m. to 3:30 p.m., Monday through Saturday. Work at all remaining locations will be from 7:00 a.m. to 7:00 p.m., Monday through Saturday.

Important Information:
* Traffic will be maintained on Rhode Island Avenue and
adjacent streets while this portion of the work takes
place.
* Some traffic stops and delays within the vicinity of the
work zones are anticipated.
* 24-hour parking restrictions will be in effect within
each work zone for a period of approximately two weeks.
* 24-hour staging for the drilling operations will be
located at each work site for approximately two weeks.

Temporary traffic signs have been set up throughout the area to alert motorists to the upcoming traffic changes.

Project Details:
DC Water is implementing its Clean Rivers Project for the District’s combined sewer system. The project includes a system of tunnels and diversion sewers for the capture of combined sewer overflows (CSOs) to Rock Creek and the Anacostia and Potomac Rivers for treatment at DC Water’s Blue Plains Advanced Wastewater Treatment Plant. The Clean Rivers Project will reduce CSOs annually by 96 percent throughout the system and by 98 percent for the Anacostia River alone.

###

About DC Water
The District of Columbia Water and Sewer Authority (DC Water), is an industry leading multi-jurisdictional regional utility that provides drinking water, wastewater collection and treatment to 600,000 residential, commercial and governmental customers in the District of Columbia, 17.8 million annual visitors and also collects and treats wastewater for 1.6 million customers in Montgomery and Prince Georges counties in Maryland and Fairfax and Loudoun counties in Virginia.

DC Water’s service area covers approximately 725 square miles and the company operates the world’s largest advanced wastewater treatment plant with a capacity of 370 million gallons per day and a peak capacity of 1.076 billion gallons per day.

Please visit dcwater.com/cleanrivers for more information on the Clean Rivers Project.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.