SMALL DIAMETER WATER MAIN REPLACEMENT PROJECT MANOR PARK AREA – ADVISORY NEIGHBORHOOD COMMISSION 4B

ADVISORY NEIGHBORHOOD COMMISSION 4B

OVERVIEW

As part of its Capital Improvement Program, DC Water is replacing existing 12-inch and smaller cast iron water mains in various locations throughout the city. Construction for this project will occur in the Manor Park area (see construction location map on back). These efforts will help improve water quality and system reliability, increase water pressure in some areas, and maintain adequate flows throughout the system.

 

 

SCOPE OF WORK

• Installation of approximately 6,091 linear feet of 6-inch up to 12-inch water mains 

• Replacement of service lines – including free private side replacement of lead and galvanized iron pipe

• Replacement of fire hydrants and valves

• Restoration of all surfaces disturbed by the project construction upon completion of the work

 

SCHEDULE 

• Estimated construction start: July 2024

• Estimated construction completion: October 2024

• Normal work hours: 9:30 AM to 3:30 PM, Monday through Friday

 

The contractor may, at times, need to work at night or on weekends, dependent upon certain construction activities, or due to inclement weather.

 

IMPORTANT INFORMATION 

• If a planned temporary water service shut-off is necessary, affected residents will be notified 48 hours in advance. Service interruptions will be minimal.

• Construction may cause temporary discolored water or low water pressure. If you experience discolored water, flush cold water taps for 15 minutes. If water does not clear, contact the DC Water Drinking Water Division or 24-hr Emergency/Command Center.

 

TRAFFIC 

• Lane closures may be required daily with approved traffic plans by the District Department of Transportation (DDOT).

• Notifications regarding “No-Parking” zones will be posted 72 hours prior to construction, in certain areas in and around the job site, as required by DDOT.

 

PARTNERS

DC Water is currently working closely with DDOT to ensure minimal disruption during this project. Regular updates will also be provided to impacted residents, Advisory Neighborhood Commission 4B, Ward 4 representatives in the Mayor’s Office of Community Relations and Services, and Ward 4 Councilmember Janeese Lewis George and members of her staff.

 

Contact Information

For more information, please contact

DC Water Project Manager:  Maria Gigova (202)787-7621 / maria.gigova@dcwater.com

DC Water Project Contractor: Fort Myer Construction Corporation-Jorge Baptista (202) 359-2969

DC Water Department of Water Quality and Technology: (202) 612-3440

DC Water 24-hr Emergency/Command Center: (202) 612-3400

DC Water Office of Marketing and Communications: (202) 787-2200

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

West Potomac Park Drive SW
West Potomac Park Drive SW: New Roadway Opening

(Washington, DC) – DC Water will open West Potomac Park Drive SW, a new road constructed as a part of the Potomac River Tunnel (PRT) Project, on Mo

Latest Blog Post
Photo of Great Falls of the Potomac River with fast moving rapids going over the falls
The Critical Need for a More Resilient Water Source and Protecting the One We Have
Source Water Protection Week highlights the case for second water source.
Upcoming Meeting
Date
December 5, 2024
Time
Thursday, 2:30 PM

Upcoming Events