Fire Hydrant Flow Test

What does it mean?

Fire hydrant flow tests are conducted by DC Water at the applicant's request. The purpose of the test is to determine the hydraulic characteristics of the water distribution system at the location of their project site. This information is used by the engineer in designing the fire suppression system, calculating the size of the domestic and fire water services to the building and to size booster pump(s) if needed.

Does this apply to me?

If the project requires a domestic service connection of 3-inches in diameter or greater or has a fire demand in excess of 100 GPM, then a hydrant flow test is needed.

DC Water will require a current fire hydrant flow test be submitted with the permit application. Current means within one year of issuance of either DC Water's Water and Sewer Availability Certificate or DOB’s building permit. In accordance with NFPA code a current hydrant flow test is required to support the fire suppression system computations for the building.

Flow tests are not needed by DC Water for the design of single-family houses where the fire protection flow rate is less than 100 GPM. A fire supply sufficiency letter can be obtained from DC Water for small fire services (100 GPM or less) which may satisfy DOB requirements.

When do I apply?

It is best to apply early - during the initial design process. A fire hydrant flow test must be obtained prior to engineering the building's domestic and fire water services for the building. The mechanical/electrical/plumbing engineer uses this information to complete the meter sizing worksheet and booster pump form.

What do I need to submit?

Please have the following information in your request package:

1. A letter, on company letterhead, requesting a fire hydrant flow test. Please include an email address and/or fax number of the person(s) that you would like the results of the flow test sent.

2. A map showing the project site location and indicate the water main(s) where you intend to establish your connection. DC Water will determine the hydrants to conduct the flow test.

3. A check or money order made payable to DC Water in the amount as shown in Fees & Charges.

Where do I go and apply?

Please email request to application@dcwater.com, mail, or drop off the application to:

Please mail or drop off the application to:
Permit Operations 
Attn: Fire Hydrant Flow Test Request
1385 Canal Street SE,
Washington, DC 20003

How long will it take?

30 days depending upon weather and emergency workload.

Please note that during winter months (when the average temperature is below 40 degrees Fahrenheit) hydrant flow tests are generally not performed due to potential risk of icing and will generally take more than 30 days to be processed.

What do I Receive?

You will receive a report that includes the static and residual pressure of the main and the flow rate at each hydrant. The report will be delivered by email to the attention of the contact indicated in the request letter.

Related Activities:

For larger projects (NFPA fire demand exceeds 100 GPM), the next activity following the hydrant flow test is typically submission of the preliminary site plan to DC Water for review and subsequent approval.

For more Info, call:

Permit Operations Department at 202-646-8600.

Regulatory Info

DC Building Code and NFPA governing the fire suppression system design require a current hydrant flow test in additional to the requirement by DC Water.

Additional Information:

On occasion there are hydrant flow test that have been performed on the same hydrants that you are requesting (nearby projects that you see are under construction) that may be applicable for your project. If the flow data is current it can be used in lieu of a new hydrant flow test.

These results can be obtained by calling the Permit Operations Department at 202-646-8600. Please have the address of the adjacent site that you think may have the recent flow test results.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Christening of TBM Emily with DC Water Interim General Manager Matt Brown holding bottle of tap water to christen Emily
DC Water Welcomes the Community Underground to See the Potomac River Tunnel and Christens Tunnel Boring Machine Emily

DC Water celebrated the christening of Emily today. It’s the second giant tunnel boring machine (TBM) that will help build the 5.5-mile Potomac River Tunnel. The celebration continued with Community Day. Residents and families met Emily and stepped inside the tunnel where she will soon begin digging.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting
Date
September 24, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.