WASA Multi-Million Dollar Biosolids Project Put on Hold

October 05, 2006

Officials at the District of Columbia Water and Sewer Authority (WASA) have decided, after an extensive and rigorous evaluation, to reject the single bid received on the construction phase of the Egg-Shaped Digester project. The bid for that phase of the project was approximately 64 percent over WASA’s 2006 budget estimate. The total project cost has, in fact, has continued to escalate from the originally budgeted $148 million in 2000 to $350 million in 2006 to an estimated $600 million in 2007.

The use of egg-shaped digesters is a progressive and effective technology for handling biosolids (treated residue from the wastewater treatment process) generated at WASA’s Blue Plains Advanced Wastewater Treatment Plant. Currently, more than 1300 wet tons of biosolids are hauled each day from the 150-acre site for reuse as fertilizer.

The eight, 108-foot-tall egg-shaped digesters, at 4.5 million gallons each, represented the largest single installation of its type in the world. The technology would reduce biosolids volume by 50 percent and cut in half the 70 trucks a day used to haul biosolids to agricultural sites in surrounding areas. The project was scheduled to begin in 2006, with the first digesters in service by 2010.

The decision by the WASA Board of Directors to defer the project until market conditions improve was based on an independently conducted economic analysis and an internal cost-benefit evaluation. Both assessments concluded that the unusually tight construction market, an abnormal spike in material costs and the project length were major factors in limiting bids and doubling the cost. Moreover, an evaluation of bids on other heavy wastewater-related construction projects in the D.C. metro area show similar cost increases that are well above estimates.

“As part of our ongoing biosolids management program, we will monitor the construction market, regulatory initiatives and evolving wastewater treatment technologies,” WASA General Manager Jerry N. Johnson said. “With this and other information collected over the next three years, a revised strategy for long-term biosolids management, which may or may not include the digesters, will be presented to our Board.”

WASA’s award-winning Biosolids Management Program has been recognized by the U.S. Environmental Protection Agency for its outstanding operations, technological advances, and promotion of the beneficial uses of municipal wastewater biosolids.

###

Latest News

The TBM named Emily at the Herrenknecht factory in Germany

Final TBM prepares for shipment from Germany to DC, marking a major milestone in the Clean Rivers Program

Map of construction area on Clara Barton Parkway near I495

DC Water will be doing construction as part of a sanitary sewer rehabilitation project on Clara Barton Parkway in Maryland from Sept 8 - Oct 10, 2025, which may cause delays inbound near the I-495 Beltway interchange. One lane will be closed in the work zone to reline an 800-foot section of the sewer line, known as the Potomac Inteceptor. Access to the inner and outer loops of the Beltway will remain available. Additional lane closure may be necessary intermittently through Oct 31, 2025.

Graphic showing LFDC work on a block, date and time of the virtual meeting

There’s more than one way to replace your lead service line. Join DC Water’s Lead Free DC (LFDC) team and explore the options available to you during our virtual meeting on Wednesday, October 22, from ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

The TBM named Emily at the Herrenknecht factory in Germany
Tunnel Boring Machine Emily Passes Key Factory Test for DC Water Potomac River Tunnel Project

Final TBM prepares for shipment from Germany to DC, marking a major milestone in the Clean Rivers Program

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
October 28, 2025
Tuesday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.