WASA Multi-Million Dollar Biosolids Project Put on Hold

October 05, 2006

Officials at the District of Columbia Water and Sewer Authority (WASA) have decided, after an extensive and rigorous evaluation, to reject the single bid received on the construction phase of the Egg-Shaped Digester project. The bid for that phase of the project was approximately 64 percent over WASA’s 2006 budget estimate. The total project cost has, in fact, has continued to escalate from the originally budgeted $148 million in 2000 to $350 million in 2006 to an estimated $600 million in 2007.

The use of egg-shaped digesters is a progressive and effective technology for handling biosolids (treated residue from the wastewater treatment process) generated at WASA’s Blue Plains Advanced Wastewater Treatment Plant. Currently, more than 1300 wet tons of biosolids are hauled each day from the 150-acre site for reuse as fertilizer.

The eight, 108-foot-tall egg-shaped digesters, at 4.5 million gallons each, represented the largest single installation of its type in the world. The technology would reduce biosolids volume by 50 percent and cut in half the 70 trucks a day used to haul biosolids to agricultural sites in surrounding areas. The project was scheduled to begin in 2006, with the first digesters in service by 2010.

The decision by the WASA Board of Directors to defer the project until market conditions improve was based on an independently conducted economic analysis and an internal cost-benefit evaluation. Both assessments concluded that the unusually tight construction market, an abnormal spike in material costs and the project length were major factors in limiting bids and doubling the cost. Moreover, an evaluation of bids on other heavy wastewater-related construction projects in the D.C. metro area show similar cost increases that are well above estimates.

“As part of our ongoing biosolids management program, we will monitor the construction market, regulatory initiatives and evolving wastewater treatment technologies,” WASA General Manager Jerry N. Johnson said. “With this and other information collected over the next three years, a revised strategy for long-term biosolids management, which may or may not include the digesters, will be presented to our Board.”

WASA’s award-winning Biosolids Management Program has been recognized by the U.S. Environmental Protection Agency for its outstanding operations, technological advances, and promotion of the beneficial uses of municipal wastewater biosolids.

###

Latest News

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Picture of repaired segment before the geopolymer work and after the work is done

Crews also reach a major milestone near Dulles International Airport as the next phase of repairs begins this week

DC Water has completed the first major step in emergency repairs to a 175-foot section of the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews added a new, stronger lining inside the pipe after inspections found serious wear and damage. The work is part of ongoing repairs to 1,700 linear feet of pipe near Pennyfield Lock. Work began on Friday to apply geopolymer, a concrete-like material, inside the pipe. With the new lining complete, crews are preparing for the next phase of work for the remainder of the pipe segment.

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.