UPDATE: Potomac Interceptor Overflow, February 3, 2026

February 03, 2026
Picture of the work site where cleaning is taking place and pumps being installed

Potomac Interceptor Overflow Update
Tuesday, February 3, 2026

 Work to clean and repair the damaged section of the Potomac Interceptor continues, though progress is being slowed by large boulders and rocks inside the pipe. Meanwhile, increased flow from groundwater infiltration attributed to snowmelt, along with periodic clogging of the bypass pumps, at times, resulted in minor overflows near the collapse site. To address these issues, crews are constructing an earthen dam in the nearby stormwater ditch to contain these minor overflows.

The 72-inch section of the sewer line collapsed along Clara Barton Parkway at the 495 interchange and the C & O Canal National Historical Park on January 19. The following is a summary of today’s efforts.

Cleaning Efforts

  • Crews continue to work on removing debris and obstructions from inside the collapsed section of the pipe. While high-powered vacuuming equipment has been effective, large rocks and boulders remain inside, complicating and slowing progress.Large rocks from inside the pipe that were too large for the vacuum
  • Specialized equipment is being mobilized to allow crews to manually remove these larger materials.
  • To date, approximately 18 tons of debris has been cleared since cleaning began.
  • It is estimated that several hundred tons of debris will need to be removed before repairs can begin to restore full flow to the Potomac Interceptor.

Containment

  • Bypass pumping operations and the existing flow through the damaged pipe are containing most of the flow, but some minor overflows have entered the creek bed adjacent to the site.
  • While these overflows are limited, it is possible that small amounts of wastewater may have reached the river.
  • Snowmelt is increasing groundwater infiltration into the sewer line, raising the volume of flow inside the Potomac Interceptor and contributing to these limited overflow events.
  • To further reduce the risk of overflows, a small earthen dam is being built around the work site to contain overflow that escapes the immediate site and prevent the wastewater from reaching the Potomac River.
  • Small, supplemental pumps are being installed within the containment area to manage minor infiltration and seepage for worker safety as they manage cleaning operations inside the excavation.

Bypass Pumping Operations

  • Efforts to contain the flow remain challenging due to recurring clogs that require pumps to be taken out of service for cleaning.
  • These clogs are often caused by wipes that do not dissolve and can trap fats, oils, and grease, leading to the pumps coming offline for service.
  • DC Water reminds the public fats, oils, and grease should never be poured down drains, and wipes should not be flushed.
  • Currently, eight pumps remain in operation. Pumping capacity is temporarily reduced whenever a pump is taken out of service for maintenance.
  • To protect equipment during extreme cold and potential snowfall, heat tents and heaters have been set up on site.
  • Crews are monitoring operations 24/7, allowing them to quickly address issues and ensure the bypass pump system continues to operate as safely and reliably as possible.

 

Latest News

Last gantry at the bottom of the shaft where crews connect it

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Lead Free DC Flyer with information about Virtual Community Meeting

From the first signs of construction on your block to the final steps of yard restoration, DC Water’s Lead Free DC (LFDC) program is answering residents’ top questions about the replacement process.

DC Water invites residents to join the next Lead Free DC virtual community meeting on August 26 from 7 PM – 8 PM.

Photo of Bloom and Blue Drop staff celebrating 10 years of Bloom at Blue Plains

Ten years ago, DC Water took the bold step of recycling waste from the Blue Plains Advanced Wastewater Treatment Plant into Bloom, a nutrient-rich soil product. Since then, Bloom has become a ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Last gantry at the bottom of the shaft where crews connect it
Now Fully Assembled, It’s Full Speed Ahead for the tunnel boring machine Mary and the Potomac River Tunnel

Final Gantry Completes Mobile Support Train Behind Mary Stretching More Than 700 Feet

DC Water’s tunnel boring machine Mary may be the muscle behind the Potomac River Tunnel Project, but the gantries that trail behind her form the heart, brains, and guts of the operation. Now crews have lowered and connected the final gantry section, giving Mary the tools and equipment she needs to continue tunneling north.

Latest Blog Post
Emergency supplies arranged on a table, including bottled water, canned food, a backpack, first aid kit, flashlight, phone, medication and other essential items.
Simple Ways to Stay Prepared at Home
A few simple steps can help your household prepare for severe weather and temporary water or sewer service interruptions.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.