UPDATE: Potomac Interceptor Overflow, February 3, 2026

February 03, 2026
Picture of the work site where cleaning is taking place and pumps being installed

Potomac Interceptor Overflow Update
Tuesday, February 3, 2026

 Work to clean and repair the damaged section of the Potomac Interceptor continues, though progress is being slowed by large boulders and rocks inside the pipe. Meanwhile, increased flow from groundwater infiltration attributed to snowmelt, along with periodic clogging of the bypass pumps, at times, resulted in minor overflows near the collapse site. To address these issues, crews are constructing an earthen dam in the nearby stormwater ditch to contain these minor overflows.

The 72-inch section of the sewer line collapsed along Clara Barton Parkway at the 495 interchange and the C & O Canal National Historical Park on January 19. The following is a summary of today’s efforts.

Cleaning Efforts

  • Crews continue to work on removing debris and obstructions from inside the collapsed section of the pipe. While high-powered vacuuming equipment has been effective, large rocks and boulders remain inside, complicating and slowing progress.Large rocks from inside the pipe that were too large for the vacuum
  • Specialized equipment is being mobilized to allow crews to manually remove these larger materials.
  • To date, approximately 18 tons of debris has been cleared since cleaning began.
  • It is estimated that several hundred tons of debris will need to be removed before repairs can begin to restore full flow to the Potomac Interceptor.

Containment

  • Bypass pumping operations and the existing flow through the damaged pipe are containing most of the flow, but some minor overflows have entered the creek bed adjacent to the site.
  • While these overflows are limited, it is possible that small amounts of wastewater may have reached the river.
  • Snowmelt is increasing groundwater infiltration into the sewer line, raising the volume of flow inside the Potomac Interceptor and contributing to these limited overflow events.
  • To further reduce the risk of overflows, a small earthen dam is being built around the work site to contain overflow that escapes the immediate site and prevent the wastewater from reaching the Potomac River.
  • Small, supplemental pumps are being installed within the containment area to manage minor infiltration and seepage for worker safety as they manage cleaning operations inside the excavation.

Bypass Pumping Operations

  • Efforts to contain the flow remain challenging due to recurring clogs that require pumps to be taken out of service for cleaning.
  • These clogs are often caused by wipes that do not dissolve and can trap fats, oils, and grease, leading to the pumps coming offline for service.
  • DC Water reminds the public fats, oils, and grease should never be poured down drains, and wipes should not be flushed.
  • Currently, eight pumps remain in operation. Pumping capacity is temporarily reduced whenever a pump is taken out of service for maintenance.
  • To protect equipment during extreme cold and potential snowfall, heat tents and heaters have been set up on site.
  • Crews are monitoring operations 24/7, allowing them to quickly address issues and ensure the bypass pump system continues to operate as safely and reliably as possible.

 

Latest News

Bypass pumps in operation to reroute wastewater around the break

Potomac Interceptor Repairs Update

February 15, 2026 

  • No overflow events impacting surface waters have been reported in the past 24 hours.
  • The four high-capacity bypass pumps installed this week are now ...
Photo of access pit upstream with four pumps lined up ready for installation

Crews have completed construction of the two new access pits to support full installation of the enhanced bypass pumping system. Three high-capacity bypass pumps have been installed and are operational, with a fourth pump expected to be activated later tonight or early Sunday ahead of the forecasted weather to help manage anticipated higher flows associated with rainfall and snowmelt.

Placeholder DC Water Image

No overflow events impacting surface waters have been reported in the past 24 hours as crews continue advancing construction of the two new access pits to support full installation of the enhanced bypass pumping system. Additional high-capacity bypass pumps are on site in advance of the forecasted weather on Sunday to help manage anticipated higher flows associated with rainfall and snowmelt.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.