UPDATE: Potomac Interceptor Overflow, February 3, 2026

February 03, 2026
Picture of the work site where cleaning is taking place and pumps being installed

Potomac Interceptor Overflow Update
Tuesday, February 3, 2026

 Work to clean and repair the damaged section of the Potomac Interceptor continues, though progress is being slowed by large boulders and rocks inside the pipe. Meanwhile, increased flow from groundwater infiltration attributed to snowmelt, along with periodic clogging of the bypass pumps, at times, resulted in minor overflows near the collapse site. To address these issues, crews are constructing an earthen dam in the nearby stormwater ditch to contain these minor overflows.

The 72-inch section of the sewer line collapsed along Clara Barton Parkway at the 495 interchange and the C & O Canal National Historical Park on January 19. The following is a summary of today’s efforts.

Cleaning Efforts

  • Crews continue to work on removing debris and obstructions from inside the collapsed section of the pipe. While high-powered vacuuming equipment has been effective, large rocks and boulders remain inside, complicating and slowing progress.Large rocks from inside the pipe that were too large for the vacuum
  • Specialized equipment is being mobilized to allow crews to manually remove these larger materials.
  • To date, approximately 18 tons of debris has been cleared since cleaning began.
  • It is estimated that several hundred tons of debris will need to be removed before repairs can begin to restore full flow to the Potomac Interceptor.

Containment

  • Bypass pumping operations and the existing flow through the damaged pipe are containing most of the flow, but some minor overflows have entered the creek bed adjacent to the site.
  • While these overflows are limited, it is possible that small amounts of wastewater may have reached the river.
  • Snowmelt is increasing groundwater infiltration into the sewer line, raising the volume of flow inside the Potomac Interceptor and contributing to these limited overflow events.
  • To further reduce the risk of overflows, a small earthen dam is being built around the work site to contain overflow that escapes the immediate site and prevent the wastewater from reaching the Potomac River.
  • Small, supplemental pumps are being installed within the containment area to manage minor infiltration and seepage for worker safety as they manage cleaning operations inside the excavation.

Bypass Pumping Operations

  • Efforts to contain the flow remain challenging due to recurring clogs that require pumps to be taken out of service for cleaning.
  • These clogs are often caused by wipes that do not dissolve and can trap fats, oils, and grease, leading to the pumps coming offline for service.
  • DC Water reminds the public fats, oils, and grease should never be poured down drains, and wipes should not be flushed.
  • Currently, eight pumps remain in operation. Pumping capacity is temporarily reduced whenever a pump is taken out of service for maintenance.
  • To protect equipment during extreme cold and potential snowfall, heat tents and heaters have been set up on site.
  • Crews are monitoring operations 24/7, allowing them to quickly address issues and ensure the bypass pump system continues to operate as safely and reliably as possible.

 

Latest News

Graphic with meeting information

DC Water is inviting Maryland residents to join us tonight for a community meeting at Walt Whitman High School at 7 p.m. for an update about ongoing repair efforts on a section of the Potomac Interceptor sewer line that failed, directly impacting the surrounding Montgomery County communities. The meeting will provide an opportunity for residents to ask questions, learn about planned environmental restoration efforts, and next steps in the emergency repair and long-term rehabilitation efforts.

Photo of remaining rocks and debris

DC Water has made significant progress toward repairing a damaged section of the Potomac Interceptor. Crews are nearly done removing a rock and debris dam that was blocking the pipe. Several feet of rocks and debris remain to be cleared and is expected to be completed overnight. Ongoing work continues to maintain bypass pumping operations 24/7 with no overflows reported for 17 days.

Graphic with the information for the Community Meeting

As DC Water continues repair efforts on the Potomac Interceptor sewer line, we want to provide an opportunity for the community to engage with us on Wednesday, February 25, to ask questions, and learn more about the response, impacts to the Potomac River, and next steps in the emergency repair and long-term rehabilitation efforts.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.