Traffic Advisory: Northeast Boundary Tunnel Shaft Excavation Work to Begin at 4th Street, NE

June 05, 2019

(Washington, DC) – In preparation for construction associated with the DC Water Northeast Boundary Tunnel (NEBT) (dcwater.com/NEBT),  DC Water's contractor will begin staging for shaft excavation activities on 4th Street, NE at the intersection of Rhode Island Avenue, NE. This will require the current work site on 4th Street to be expanded into one lane on Rhode Island Avenue. Subsequently, westbound traffic on Rhode Island Avenue will be reduced from three lanes to two lanes as it moves past the construction site. Once past the intersection at 4th Street, motorists can again utilize three travel lanes. Shaft excavation activities will begin on or about Monday, June 3, 2019.

Work hours will be 7 am to 7 pm, Monday through Friday and will take approximately 1 month to complete. Access to the businesses in the vicinity will remain open during construction activities.

Traffic and Pedestrian Restrictions

Travel Restrictions:

Westbound Rhode Island Avenue, NE - traffic will merge into two-lanes of travel left around the 4th Street, NE construction and then return to three-lane travel immediately past the intersection.

Pedestrian Impacts:

The pedestrian crosswalk across 4th Street, NE at the Rhode Island Avenue, NE intersection will be closed for approximately 1 month. Detour signs will guide pedestrians to safely cross Rhode Island Avenue and the southern intersection of 4th Street.

Safety Information

  • Commuters and pedestrians will notice road signs and/or flagging personnel directing them around the work site. Please obey road crew flaggers and pay attention to signage.
  • As a result of the construction work, commuters may experience congestion within the 250-foot designated work area. Please do not tailgate, keep a safe distance, and don’t drive distracted.
  • Please be patient and stay calm. Plan to allow extra time while traveling around the area. Check real-time traffic apps and the NEBT website for updated traffic impacts.

Additional Information

  • Access to all businesses in the vicinity will remain open during construction activities. Motorists will see flaggers guiding them into the BP Gas Station at the corner of 4th and Rhode Island Avenue, NE if they choose to enter.
  • People who live or work near the affected locations will notice additional construction equipment and personnel as well as noise associated with construction activities.

Project Details

The Northeast Boundary Tunnel is the largest component of the Clean Rivers Project. It begins south of RFK Stadium and will extend north to Rhode Island Avenue, NE and west to 6th Street, NW. When complete, the approximately five-mile long tunnel will significantly reduce chronic flooding in areas it serves.


###

For more information, please contact

Email: dccleanrivers@dcwater.com

24/7 NEBT Hotline: (800) 988-6151

Northeast Boundary Tunnel Project Website: dcwater.com/NEBT

Latest News

Excavators in the canal digging up soil and another excavator removing the soil to a dump truck to be hauled away

DC Water and its contractor have made significant progress on soil removal, reaching the clay liner between locks 13 and 14 of the C & O Canal, which was used as a bypass for wastewater during the Potomac Interceptor repairs.

Work continues to remove sludge between locks 10 and 13, which is expected to be completed by mid- to late-April. The soil will then be removed down to the clay liner as the final step, and the canal reconstructed to meet National Park Service specifications.

Soil Removal Underway with Excavator in Canal

Today, DC Water and its contractors began removing contaminated soil between locks 13 and 14 in the C & O Canal, which was used as a temporary bypass during the Potomac Interceptor repair effort. Clean-up efforts are ongoing at Lock 10 with work to remove sludge now getting underway between locks 11 and 13.

Aerial shot of Blue Plains Advanced Wastewater Treatement Plant

Series 2026 Bond Transaction Delivers Significant Long-Term Cost Savings

DC Water has closed on a refinancing deal for its Series 2026 bonds that will save customers millions of dollars and keep rates affordable across the District. The refinancing transaction, which closed this month, delivers approximately $54 million in budget savings over the next twenty years, directly benefiting DC ratepayers through reduced costs.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 7, 2026
Tuesday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.