DC Water Completes Third of Four Emergency Repairs on the Potomac Interceptor
Fourth and final repair at Pennyfield Lock is expected to be done next month
DC Water is nearing the finish line on emergency repairs to the Potomac Interceptor sewer line. DC Water and its contractors finished repairs along Clara Barton Parkway at the Maryland–DC border. It is the third of four emergency repairs identified earlier this year to be completed following a full inspection of the 54-mile sewer line.
Crews finished grouting, the final step to complete the sliplining repair. During sliplining a new pipe is placed inside the old sewer line. The new, stronger pipe restores the structural integrity and is more resistant to damage from corrosion. The grout fills the space around the new pipe sections and holds it in place.
With the repair complete, crews sent a camera through the pipe. This closed-circuit television (CCTV) inspection lets them see inside, check the new lining, and make sure the work is sound before wastewater flow was returned to the pipe.
Two other repairs were finished earlier this summer, at Dulles International Airport and Broad Run in Loudoun County.
That leaves one repair to go. At Pennyfield Lock, the fourth and final site, crews this week finished sliplining about 1,700 feet of sewer line. Wastewater flow is expected to return to that pipe next week and the repair completed in December. At that time, site restoration will begin.
This work is part of DC Water’s ongoing efforts to address critical infrastructure needs and maintain reliability of the Potomac Interceptor. This large sewer carries wastewater from communities in Northern Virginia and Maryland to DC Water’s Blue Plains Resource Recovery Facility.
Even after the final repair is done, more work is coming. In 2027, DC Water plans a second phase of high-priority repairs on more upstream sections of the Potomac Interceptor. Crews will use the same construction site at the Maryland–DC border.
Keeping the site means crews can keep working without building a new work area. One excavation pit will stay open for this future work. The other openings will be backfilled, and the area will be fully restored after Phase 2 is complete.
All of this is part of DC Water’s 10-year, $625 million Potomac Interceptor Rehabilitation Project. The project is part of DC Water’s Capital Improvement Program, which invests in aging water and sewer infrastructure.
To learn more about the Potomac Interceptor Rehabilitation Project, visit dcwater.com/potomacinterceptor.