Sinkhole at 17th Street, NW, Diverts Traffic for Sewer Repairs

January 24, 2019
Sewer Repairs

DC Water crews remain on the scene of a hole that opened in the roadway at 17thand D Streets, NW. DC Water is currently continuing excavations and shoring of a trench to expose a 39” x 58” sewer that was damaged.

The repairs are expected to take close to a week and require road closures as follows:

  • 17th Street, between C and E Streets, NW; and
  • D Street, between 15th and 17th Streets, NW

A DC Water sewer investigator yesterday determined that a section of an egg-shaped 39” by 58” sewer line was crushed when concrete fell on it.
 
So far, the PEPCO lines involved have been de-energized of their 230,000 volts of electricity. There are no other utilities affected, but the repair is complex. Once the sewer damage is exposed and assessed, repairs can begin. After the repair, PEPCO will return to restore the power lines, which will be followed by the restoration of the roadway.
 
DC Water will provide updates throughout the process, which may take up to a week or more. The intersection remains closed to vehicular traffic at this time.

Latest News

Workers manually removing soil between the locks

Work is progressing on the clean-up for the C & O Canal which was used as a bypass while the Potomac Interceptor was repaired. Workers are focused on removing sludge between locks 11 and 12. Soil removal is also nearly complete between locks 12 and 14, reaching the canal's clay liner. Workers are now manually removing additional materials in some areas.

Excavators in the canal digging up soil and another excavator removing the soil to a dump truck to be hauled away

DC Water and its contractor have made significant progress on soil removal, reaching the clay liner between locks 13 and 14 of the C & O Canal, which was used as a bypass for wastewater during the Potomac Interceptor repairs.

Work continues to remove sludge between locks 10 and 13, which is expected to be completed by mid- to late-April. The soil will then be removed down to the clay liner as the final step, and the canal reconstructed to meet National Park Service specifications.

Soil Removal Underway with Excavator in Canal

Today, DC Water and its contractors began removing contaminated soil between locks 13 and 14 in the C & O Canal, which was used as a temporary bypass during the Potomac Interceptor repair effort. Clean-up efforts are ongoing at Lock 10 with work to remove sludge now getting underway between locks 11 and 13.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
April 10, 2026
Friday, 9:30 AM

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.