Overnight Storm First Major Test of DC Water’s New Anacostia River Tunnel

April 16, 2018
Photo of Anacostia Tunnel

DC Water’s newly opened Anacostia River Tunnel System was pressed into service overnight as heavy rains battered the District of Columbia. About two inches of rain fell over a three hour period, far more than the city’s combined sewer system can handle. During the storm, the new tunnel prevented approximately 170 million gallons of combined sewage and stormwater from being discharged to the Anacostia River.

DC Water placed into operation the first section of the Anacostia River Tunnel System, from RFK Stadium to the Blue Plains Advanced Wastewater Treatment Plant, in late March. This portion of the system comprises about seven miles of 23’ inside diameter tunnel that can store more than 100 million gallons, while continuously processing another 225 million gallons per day at the new Wet Weather Treatment Facility at Blue Plains. 

Henderson Brown, DC Water’s Interim CEO and General Manager, said, “In its first real test, the new tunnel system worked as designed, storing – then treating—millions of gallons of combined sewage that otherwise would have overflowed to the river. That is great news for the Anacostia, and it will only get better when the rest of the tunnel system is brought online.”

During the storm the new tunnel filled to capacity.  Based upon preliminary data analysis, the flow exceeded the tunnel capacity by between 10 and 20 million gallons, which overflowed to the Anacostia River.   The next portion of the Anacostia River Tunnel system, the Northeast Boundary Tunnel now under construction, will add approximately 90 million gallons of storage when it is placed into service in 2023.

As in many older cities, about one-third of the District has a combined sewer system. A combined sewer overflow (or CSO) occurs during heavy rain when the mixture of sewage and stormwater cannot fit in the sewer pipes and overflows to the nearest water body. CSOs contain bacteria and trash that can be harmful to the environment, but the system was designed as a preferable alternative to the combined sewage backing up in homes and businesses and on the streets. Since the early 1900s, only sewer systems with separate pipes for sewage and stormwater have been installed in the District. CSO tunnels similar to DC Water’s already exist in Chicago, Indianapolis, Atlanta and other cities.

Once the Anacostia Tunnel System is completed, overflows may still occur in rare, intense rainstorms, but the tunnels will capture 98 percent of the CSOs in an average year.

For more information on the Clean Rivers Project, please visit www.dcwater.com/cleanrivers.

Latest News

Photo of completed repair with concrete encasing the sewr pipe

DC Water has successfully completed emergency repairs on a critical section of the Anacostia Force Main following a failure near Anacostia Avenue and Ponds Street Northeast in July. With repairs finalized, attention now turns to rehabilitating other vulnerable segments of the 6.25-mile pipeline to ensure long-term reliability and resilience. 

Map of construction area on Clara Barton Parkway near I495

DC Water will be doing construction as part of a sanitary sewer rehabilitation project on Clara Barton Parkway in Maryland from Sept 8 - Oct 10, 2025, which may cause delays inbound near the I-495 Beltway interchange. One lane will be closed in the work zone to reline an 800-foot section of the sewer line, known as the Potomac Inteceptor. Access to the inner and outer loops of the Beltway will remain available.

Rock Creek Trail Site for Potomac River Tunnel Project

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Rock Creek Trail Site for Potomac River Tunnel Project
Ground Stabilization Work Begins Near Watergate Complex, starting Aug 25

Starting the week of August 25, DC Water will take another big step forward in the Potomac River Tunnel Project. Ground stabilization will begin at the Rock Creek Trail site, near the Watergate Complex, to drill secant piles that will form a retaining wall for the drop shaft.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
September 18, 2025
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.