Soil Removal in C & O Canal reaches half-way point with locks 12-14 complete

April 14, 2026
Photo of soil removal and excavation
  • DC Water and its contractor have removed all the soil down to the clay liner between locks 12 and 13, marking 50% completion of the canal clean-up. Soil removal between Locks 13 and 14 was completed earlier this month.
  • Clean-up efforts continue between locks 10 and 12, with sludge removal complete and soil removal now underway.
  • As crews complete soil removal, work is underway to clean the historic locks as prescribed by the National Park Service. Cleaning at Lock 13 has been completed, and work is underway at Lock 12.
  • DC Water is also coordinating with NPS to rebuild sections of the C & O Canal used as a bypass during Potomac Interceptor repairs, once soil removal is complete. In preparation, a clay supplier has been identified to repair the clay liner and restore the canal to NPS standards.
  • Site preparations continue for the previously planned long-term rehabilitation of the Potomac Interceptor, which has been accelerated to address more than 2,700 linear feet in the area where the pipe failure occurred.
  • Crews are excavating a third site outside the I-495 Beltway, that will be used to rehabilitate the pipe using a process called slip lining. New pipe sections will be inserted into the existing pipe at three locations with long, straight stretches. This includes the two locations of the pipe – at the collapse site and the bypass pumping site – that remain open to more efficiently complete the slip lining process. This approach creates a new pipe within the existing pipe, strengthening and reinforcing the interceptor to a like new structural condition.

Photo of clay liner upstream from Lock 12 where soil removal complete

Water Quality Sampling Results

It is important to understand that rain, snow, heat, contaminated runoff, and natural sources of E. coli such as wildlife, can cause elevated bacteria levels in urban rivers like the Potomac River. 

Because there have been no overflows to the river from the Potomac Interceptor for more than a month prior to the completion of emergency repairs, fluctuations in sampling results are more likely due to these other known factors.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is available on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Water Quality Sampling Results graphic

Sample results from March 23 - present are below. Past results may be found here.

 

 

 

 

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.