EMERGENCY WATER OUTAGE
Nov 22, 2026 | 03:53 PM

EMERGENCY WATER OUTAGE
Nov 22, 2026 | 06:00 AM

LTCP Engineering Services

March 10, 2008

The District of Columbia Water and Sewer Authority (DCWASA or Authority) will be moving into the detailed design and construction phases of its Long Term Control Plan (LTCP) for the District’s combined sewer system. The LTCP comprises a system of deep tunnels, diversion structures and sewers and ancillary facilities to control combined sewer overflows to the Anacostia and Potomac Rivers and Rock Creek. The principal features of the system include about 8500 ft of 34 ft diameter, 3000 ft of 25 ft diameter, 53,000 ft of 23 ft diameter and 11,000 ft of 15 ft diameter tunnels.

The Authority will require a variety of professional engineering services for LTCP implementation and will hold an information meeting for firms interested in being considered to provide these services. The Authority will present its organization, program and schedule and entertain questions and comments at the meeting and for a short period following the meeting.

The Authority anticipants that agreements for these services will be subject to a Fair Share Objective for Minority and Women Business Enterprises (MBE and WBE) participation of 28 percent and 4 percent, respectively as a minimum. The program requirements are defined in the USEPA’s “Guidance for Utilization of Small, Minority and Women’s Business Enterprises in Procurements Under Assistance Agreements – 6010, 1997 Edition”.

The meeting will be held on March 20, 2008 from 9:00 a.m. to 12:00 noon at the Authority’s Central Operations Facility building (on the Blue Plains Advanced Wastewater Treatment Plant site), 4th Floor, Room 409, 5000 Overlook Avenue, SW, Washington, D.C. 20032.

Space will be limited and firms attending are requested to limit attendance to two (2) persons. Firms planning to attend should make reservations by telephone or email to Ms. Melva Massey at (202) 787-2363 or mmassey@dcwasa.com. Reservations should be made no later than March 18, 2008. If space becomes limited, reservations will be given preference.

Persons attending will have to obtain a visitor’s pass at the plant entrance security building and should plan for 30 to 60 minutes to complete this process. The Central Operations Facility building is immediately to the right of the entrance gate and parking will be available in designated areas around the building.

For more information, please refer to the information document attached below.

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.