DC Water Moves Forward with Major Sewer Line Repairs to Protect Rock Creek

September 29, 2025
Picture showing inside of Rock Creek Main Interceptor with large crack in crown

DC Water is advancing to the next critical phase of the Rock Creek Main Interceptor (RCMI) repair project, following the discovery in May of structural vulnerabilities in the 72-inch diameter sewer line that carries over 100 million gallons of wastewater daily. These repairs are a high priority to prevent potential sewage discharge into Rock Creek and are part of DC Water’s Capital Improvement Program.

To safely begin Phase 1 construction, a section of the Rock Creek Multi-Use Trail will be closed for two days:

  • Closure Start: Friday, October 3, 2025 at 8 PM
  • Closure End: Sunday, October 5, 2025 at 8 PM
  • Trail Segment: Between P Street NW and Pennsylvania Avenue NW
  • Detour: Available via Rose Park
  • Work Hours: Continuous, 24/7 throughout the weekend

During the gate restoration, one lane of southbound Rock Creek and Potomac Parkway NW will also be closed.

Map of full project area next to map of Rock Creek Trail Site

 

This initial phase focuses on restoring one of two gates located within a structure along the trail—an essential step before internal pipe inspections and full-scale repairs begin in Phase 2 later this fall.

The gates being restored are critical to managing wastewater flow during construction and wet weather events. Located at key points along the RCMI system—including near the Smithsonian National Zoo, Rock Creek Trail near Rose Park, and the Georgetown Waterfront—these gates allow DC Water to divert flow away from active work zones. During heavy rain, the gates can be opened to increase system capacity and reduce the risk of overflow, helping protect both the infrastructure and the surrounding environment.

Looking ahead, Phase 2 of the rehabilitation project will involve internal restoration of approximately 3,000 feet of the 72-inch diameter pipe and is expected to run through September 2026.

DC Water appreciates the public’s patience and cooperation as crews work to safeguard the integrity of this vital infrastructure. Noise and traffic impacts will be monitored throughout the project, and updates will be shared regularly.

 

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.