DC Water Completes Critical Potomac Interceptor Sewer Line Repairs at Broad Run

September 03, 2026
Photo of manhole entrance withe completed geopolymer
Second of four high-priority repair projects is now complete

DC Water has completed the second of four critical repair projects on the Potomac Interceptor Sewer Line. Crews finished strengthening a 490-foot section of the pipe at Broad Run in Loudoun County today.

Work began in June after inspections found serious damage inside the 54-mile sewer line. Crews found corrosion, worn concrete and exposed steel supports. They repaired this 42-inch-wide section with a strong new lining using a concrete like material. Next a flexible liner was installed inside the pipe that was hardened in place to form a new pipe inside the existing one. Together, these repairs restored the pipe to like-new condition.

Broad Run is one of four locations that DC Water identified earlier this year for critical repairs. Work continues at Pennyfield Lock in Potomac, Maryland, and along Clara Barton Parkway near the Maryland-DC line. Last month, DC Water also completed repairs to a 600-foot section of ther Potomac Interceptor near Dulles International Airport.

Now that the pipe repairs are complete, DC Water will begin work to restore the Broad Run site.

Emergency repairs continue at the two remaining locations.

Pennyfield Lock

At Pennyfield Lock work is underway to prepare for the next phase of repairs. Crews are digging two large pits that will be used to place new pipe sections inside the existing pipe. Due to groundwater issues, crews are adding pumps and other safeguards to keep the pits dry. This work is taking longer than expected and may delay the start of pipe installation beyond September.

The possible schedule change is not expected to cause serious issues. The most critical section of pipe was repaired in late July. DC Water strengthened 175 feet of the sewer line where inspections found major corrosion and exposed steel supports. Crews added a new, stronger lining inside the pipe. This earlier repair helps protect the pipe while crews manage groundwater and prepare to repair the remainder of the 1,700 linear foot rehabilitation project.

Maryland-DC Line

Work also continues along Clara Barton Parkway near the Maryland-DC line. Crews have installed a temporary bypass pumping system, and it is now operating at the site. The system keeps wastewater flowing safely around the section under repair.

Crews are now adding a strong new lining inside the existing pipe. This will stabilize the pipe and allow crews to safely complete the permanent repair.

After the lining is complete, crews will prepare to place a new pipe inside the existing sewer line. The new pipe is designed to better resist corrosion, strengthen the sewer line and extend the life of the pipe for decades to come.

To do the work, sections of the pipe are open to pump the wastewater out and back into the pipe downstream. Another opening will be used to insert the new pipe section while wastewater continues to flow through the open sewer line. During this time, people may notice odors in the immediate area around the site. These odors, while unpleasant, do not pose a health risk. DC Water is working to add odor control measures to try and help reduce the smell.  

For more information about the Potomac Interceptor repairs, visit dcwater.com/potomacinterceptor.

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.