UPDATE: Potomac Interceptor Sewer Overflow Incident, February 7

February 07, 2026
Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

Potomac Interceptor Update

Saturday, February 7, 2026

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

With no overflows reported from the site yesterday and today, water quality sampling for E.  coli continues to trend downward at the Lock 10 channel where the overflow occurred. Sampling results at downstream sampling locations continue to remain within EPA standards for acceptable levels.

Here is an update on today’s work:

Containment

  • No overflows reported today.
  • Crews continue to monitor bypass pumping operations 24/7, performing routine cleaning and maintenance to ensure continued pumping capacity and reliability.

Pipe Cleaning Efforts

  • Excavation was completed at the pit near the I-495 interchange and Clara Barton Parkway to access a section of the Potomac Interceptor upstream of the break.
  • Trench boxes were installed around the upstream section of pipe and backfilled to stabilize the excavation.
  • Work continues on a third flume to the Potomac Interceptor as part of the bypass system, allowing wastewater to be returned to the system further downstream of the collapse site.
  • Installation of additional bypass pumps and the upstream bulkhead is expected to take 4-6 weeks from the time work began on February 6.
  • These steps are necessary before crews can begin to safely remove the blockage inside the pipe.
  • Removal of the rock and boulder obstruction will require a combination of manual work inside the pipe and the use of heavy equipment.

Water Quality Sampling Results

Grid of test results

Historical data indicate typical E. coli levels in the Potomac River can range from 10 to 5,000 MPN/100mL. Variability in E. coli results are common and are influenced by multiple factors, such as weather (rainfall/snow melt and associated runoff) and subwatershed activities and conditions, including aging sewer infrastructure and illicit discharges.

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.