UPDATE: Potomac Interceptor Oveflow, Saturday, January 31

January 31, 2026
Truck mounted vacuum cleaning the Potomac Interceptor
DC Water and its contractor continue work to mitigate the sanitary sewer overflow that occurred on January 19, from the Potomac Interceptor, along Clara Barton Parkway and the 495 interchange and into the C& O Canal National Historical Park. Below is an update on the progress. 
 
Potomac Interceptor Overflow Update
January 31, 2026
 
Containment
  • The overflow remains contained for now, with no overflows from the damaged pipe section for a third straight day. 
  • Pumping operations continue and the bypass is operating as expected. 
  • We have eight pumps running, which provides us excess capacity and redundancy. 
  • Some residual wastewater may still be in the creek bed, and the excavation work may release a small amount of wastewater into the creek bed. 
  • The risk of overflow is greatly reduced, however, the potential for dry and wet weather overflows will not be eliminated until full flow is returned to the sewer line.  
 
Repair Efforts
  • Site preparations continue for operations to begin clearing the blockage at the collapse site. 
  • Contractors today excavated and opened up another section of the Potomac Interceptor further downstream of the break. 
  • Once cleaning of the collapse site begins, some soil and debris loosened by the cleaning may flow downstream.  
  • The second location will allow another access point to capture this debris as part of the cleaning process. 
  • This work will continue on Sunday and it is expected to take several days to clean out the pipe and restore full flow, pending any unknown issues.  
 
Environmental Cleanup and Review
  • We have begun taking water samples for testing. 
  • Teams are in the process of surveying the area to develop a cleanup and restoration plan, which will be reviewed with our partner agencies at the federal, state and local level. 
 
Impact of Snow Melt
  • The C & O Canal section being used as a bypass has extra capacity that should be able to handle snow melt. 
  • With eight pumps operating, we also have additional pumping capacity should flow inside the PI increase.
  • The C & O Canal section being used for the bypass is dammed at Lock 14, preventing any snowmelt upstream from entering the bypass section and impacting water levels. 

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.