DC Water Begins Demobilizing Emergency Repair Operations, Transition to Long-Term Pipe Rehabilitation

March 17, 2026
workers spraying and mucking sludge from canal
  • After three days of stable operations following completion of emergency repairs to restore flow to the Potomac Interceptor, the bypass pumping system is being demobilized. Crews have begun disassembling the bypass pipes and removing them from the upstream section of the interceptor, where pumps were used to divert wastewater around the collapse site and back into the interceptor further downstream.
  • DC Water and its contractors continue to remove sludge and debris from the C & O Canal as part of the initial environmental rehabilitation and clean-up.
  • The initial phase of environmental rehabilitation is nearing completion in the areas directly impacted by the overflow, including the drainage channel along Clara Barton Parkway, Rock Run culvert, the unnamed tributary to the Potomac River, and the immediate shoreline along the river.
  • Some work remains in the eastern section of Area 1 within the drainage channel. The initial rehabilitation work includes clearing brush and debris, mucking, removing contaminated soil, and installing erosion control and soil stabilization measures for the initial phase of clean-up.
  • The area will remain an active construction site for the next 9-10 months, as DC Water demobilizes from the emergency repair and transitions to the previously planned long-term rehabilitation.
  • Site preparations will soon begin to bring in equipment and materials needed to rehabilitate more than 2700 linear feet of the interceptor, using a process called slip lining. A new pipe will be inserted into the existing interceptor to strengthen and reinforce it to like-new condition.
  • DC Water is also preparing for two community meetings this week to provide updates and answer questions about the repairs and environmental rehabilitation:
    • Wednesday, March 18 at 6:30 PM | Walt Whitman High School (Cafeteria) | 7100 Whittier Blvd., Bethesda, MD 20817
    • Thursday, March 19 at 7:00 PM | Lee Center Auditorium | 1108 Jefferson St., Alexandria, VA 22314
    • Those interested in attending may RSVP at events@dcwater.com. Please include which meeting you plan to attend.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. This is reflected in the March 16 sampling results that coincided with a rain event. Given these variables and that overflows have been contained for more than a month prior to completing emergency repairs, measurements taken much further downstream are likely unrelated to this incident.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Due to severe weather on Monday, we were unable to perform water quality sampling at two locations. Sampling resumed today and results will be available tomorrow.

Sample results from March 9 - present. Past results may be found here.

graphic of water quality results

For the latest updates and information, including how to provide feedback on the environmental rehabilitation, go to our dedicated Potomac Interceptor Response page.

 

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.