C & O Canal Clean Up Now Underway between Locks 13 and 14

March 18, 2026
photo of freshwater dam at lock 14 with water being pumped out
  • DC Water and its contractors are now working between locks 13 and 14 in the C & O Canal to vacuum out sludge and muck left behind by the bypass pumping system, that directed wastewater around the damaged Potomac Interceptor and back into the pipe further downstream.
  • The freshwater dam at Lock 14, is now complete, and water is being pumped into the canal to help flush out the sludge and debris, for the initial cleanup.
  • Work is progressing on the initial phase of environmental rehabilitation near Lock 10 of the canal. The clean-up has been underway since flow was restored to the interceptor on Saturday.
  • The initial phase of cleaning and temporary stabilization is nearly complete in the areas directly impacted by the overflows, including the drainage channel along Clara Barton Parkway, Rock Run culvert, the unnamed tributary to the Potomac River, and along the shoreline.

Water Quality Sampling Results

Fluctuations in water quality are influenced by factors such as rain, heat, or other weather events, river flow, runoff, pollutants, releases of combined overflows, and other sources discharging into waterways. This is reflected in the large fluctuations shown March 16 and 17, coinciding with heavy rains. As a result, it’s unlikely the changes in E. coli levels are related to the Potomac Interceptor which last had an overflow reach the river well over a month ago.

For the Potomac River, historical water quality data shows E. coli levels may vary from a range as low as 10 MPN/100mL to as much as 5,000 MPN/100mL on a given day. A more detailed explanation is posted on the District Department of Energy and Environment (DOEE) website at doee.dc.gov/release/potomac-interceptor-update-and-faqs.

Sample results from March 9 - present. Past results may be found here.

graphic of water quality sampling results

For the latest updates and information, including how to provide feedback on the environmental rehabilitation, go to our dedicated Potomac Interceptor Response page.

 

 

Latest News

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m. - 1 p.m. while tree removal equipment is delivered to DC Water’s Park Road construction site ...

Workers inside the pit pushing in the new pipe section at Pennyfield Lock
Update

Work on the Potomac Interceptor at Pennyfield Lock is moving faster than expected. Crews were able to make significant progess, finishing preparationg work to begin the permanent repair this ...

Image of DC Water mascot Wendy with a child and the Lead Free DC Logo highlighting the Ward Wide Tour

First Stop Nov 19: Enjoy Free Giveaways and Live Music While Learning about LFDC

DC Water’s Lead Free DC (LFDC) Program is going on the road with a Ward Wide Tour. We’ll be spreading the word about replacing lead service lines with fun, festive community pop-up events making stops in all eight wards.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of Piney Branch Tunnel site, including the outfall where combined stormwater and wastewater overflows are released in heavy rains
TRAFFIC ADVISORY: Temporary Road Closure for Equipment Delivery May cause delays on Park Road NW

On November 17, drivers may experience delays along Klingle Road and Park Road NW around midday 10 a.m.

Latest Blog Post
Before-and-after comparison of a 12-inch blowoff connected to a 36-inch water main near Massachusetts Avenue and Macomb Street NW. The images show the inside of the structure before the repair, repair work around the pipe, and the interior after the repair was completed.
One Repair, Millions of Gallons Saved
How Teamwork Helped DC Water Stop Hidden Water Loss
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.