Emergency Water Outage
Feb 07, 2026 | 04:00 PM

Emergency Water Outage
Feb 07, 2026 | 03:00 PM

Emergency Water Outage
Feb 07, 2026 | 03:00 PM

Nannie Completes Anacostia River Tunnel

November 07, 2016

Another DC Water tunnel boring machine (TBM) has completed her mission, creating a nearly two-and-a-half-mile-long tunnel that will be used to help improve the water quality in the Anacostia River. The TBM, named Nannie, completed the excavation of the Anacostia River Tunnel (ART) on Saturday, exactly one year and a day after she began mining on November 4, 2015.

Nannie‘s journey started in a deep shaft near RFK stadium and ended when she broke through the wall of another shaft at Poplar Point, near the intersection of DC 295 and the Suitland Parkway. The tunnel is 23 feet in diameter and runs approximately 100 feet below the surface, crossing under the Anacostia River, CSX railroad tracks and Metro’s Green Line. It connects to another tunnel completed in 2015 by a tunnel boring machine named Lady Bird.

The tunnels are part of DC Water’s Clean Rivers Project aimed at controlling combined sewer overflows to the waterways of our nation’s capital.  The project includes a system of tunnels, drop shafts and diversion structures designed to capture combined sewage, which is a mixture of storm water runoff and sanitary sewage, and deliver it to the Blue Plains Advanced Wastewater Treatment Plant.  The project also includes Green Infrastructure which uses vegetation and soil to manage stormwater where it falls.

“Our Clean Rivers Project team continues to push forward at an incredible pace, and the completion of this tunnel is another key milestone to celebrate,” said DC Water CEO and General Manager George S. Hawkins. “We applaud everyone who has played a part in keeping this work on schedule to meet our ultimate goal, which is cleaner water everyone can enjoy. That will be a great return on the investment our ratepayers are making in this massive project.”

DC Water is aggressively working toward a March 2018 deadline for placing in operation a major part of the tunnel system serving the Anacostia River from RFK Stadium south to the Blue Plains Advanced Wastewater Treatment Plant near the Wilson Bridge.  The Anacostia Tunnel was the last major tunnel to be excavated to meet the 2018 deadline.

Nannie was blessed by Cardinal Donald Wuerl, the Catholic archbishop of Washington, and visited by Vice President Joe Biden prior to starting work on the tunnel. She was named after Nannie Helen Burroughs who was an African-American educator and civil rights activist in the District.

The tunnel is being constructed by Salini-Impregilo / Healy / Parsons (IHP) joint venture. More than 38 million gallons of combined sewage can be stored in the tunnel during rain events and then slowly released to Blue Plains for treatment. You can view time lapse video of the tunnel at https://youtu.be/L0QHHRe8deU.

When the Clean Rivers Project is complete, DC Water will have reduced combined sewer overflow volume by 96% overall with a 98% reduction for the Anacostia River. For more information on the Clean Rivers Project, please visit: dcwater.com/cleanrivers

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.