District Breaks Ground on Large-Scale Flood Relief for Bloomingdale and LeDroit Park

December 07, 2012

(WASHINGTON, D.C.) -- To mitigate flooding and sewer backups in the Bloomingdale and LeDroit Park neighborhoods, Mayor Vincent C. Gray and DC Water today announced a major new infrastructure project at the site of the former McMillan Sand Filtration Plant. The Northeast Boundary Neighborhood Protection Project is a product of the Mayor’s Task Force on the Prevention of Flooding, and will be built in three phases between now and 2022.

Mayor Gray established the task force in late August and named City Administrator Allen Y. Lew and DC Water General Manager George S. Hawkins as co-chairs.

"I asked the Task Force two basic questions," said Mayor Gray. "The first is why the long-term solution to this historic problem was still more than a decade away. The second is whether anything more could be done in the interim. This project answers both questions. I applaud the Task Force and DC Water for developing it, and I want the residents of the affected communities to know that relief is on the way. It will be meaningful, and it will come soon."

The two neighborhoods are connected to an undersized sewer system and have been subject to flooding during heavy rains for more than a century. DC Water’s long-term approach to this problem, the Clean Rivers Project, is a tunnel system that will add capacity to the sewers and was originally scheduled for completion in 2025. Mayor Gray convened the Task Force and DC Water began a new investigation of causes and possible mitigation strategies after four intense storms inflicted property damage in Bloomingdale and LeDroit Park this summer.

The first phase will store a total of up to 6 million gallons of stormwater, using two existing underground basins at the McMillan site. Flow will be diverted from feeder sewers adjacent to the McMillan site, capturing stormwater before it arrives in Bloomingdale and LeDroit Park and reaches the sewer system. This will help reduce the excessive pressure that currently causes sewer backups and overland flooding during heavy rain storms.

Preparation for construction on the first phase will begin immediately, with completion projected in spring 2014. This construction will not disrupt the District’s proposed development plans for the McMillan site.

"Our engineers have literally gone back to the drawing board more than a dozen times, and the McMillan project is the result," said Hawkins. "The team has been hard at work this summer and fall, investigating and evaluating every possible approach to this problem. We’ve heard the message loud and clear that waiting the better part of a decade for the Clean Rivers Project isn’t an option. We appreciate the public’s patience, and we’re ready to deliver."

The second phase of the project will bring the construction of a 19-foot-diameter tunnel under 1st Street NW. DC Water will construct the tunnel to hold an additional 6 million gallons of wastewater and stormwater during heavy rain events, using a temporary pumping station to carry flow into the Northeast Boundary sewer after the storm passes. Completion for the second phase is projected for spring 2016.

The third phase of the project is a realignment and acceleration of the Northeast Boundary portion of the Clean Rivers Project. The new alignment will create less disruption and involve less private property during construction than the prior plan. When this section of tunnel is complete, scheduled in 2022, DC Water will convey the flow from the 1st Street tunnel to the Blue Plains Advanced Wastewater Treatment Plant.

"This project is colossal in size, scope and neighborhood impact and it’s going to require significant coordination among the agencies and ongoing communication with the community to make it work," said Lew. "We’re going to treat it like the building of a stadium or a convention center and bring together everyone we need, as often as needed, to get the job done. This project is critical because it not only helps mitigate the flooding problem, but provides much-needed additional capacity for future economic development opportunities in the area."

The Northeast Boundary Neighborhood Protection Project at the McMillan site is the latest and largest step in a series of actions by District Government and DC Water in response to the four flooding and sewer backup events in Bloomingdale and LeDroit Park last summer.

On November 1st the District Department of Transportation (DDOT) installed new catch basins (or storm drains) on the 500 and 600 blocks of Florida Avenue NW to assist with removing water from the roadway during rain events. Work was completed in late November, and a similar effort will commence in early January that will also include installation of porous pavers, tree boxes and other water-capturing features in the sidewalk along the 100 block of Rhode Island Avenue NW. Work on this project will be completed in mid-March.

The other steps have included:

- A thorough visual inspection of sewers in Bloomingdale, LeDroit Park and parts of Shaw and Columbia Heights;
- A rebate program for installing backflow preventers (backwater valves);
- Individual engineering consultations;
- A rain barrel-subsidy and installation program;
- Sandbag distribution; and
- Analysis of potential changes in plumbing and housing code.

The cost of the Northeast Boundary section of the Clean Rivers Project is estimated at $600 million, with funding from DC Water ratepayers. Accelerating the solution, adding the stormwater capture and the 1st Street tunnel will add approximately $40 million to the cost.

The Mayor’s Task Force on the Prevention of Flooding will deliver its final report to Mayor Gray by December 31. For more information on the task force, go to www.oca.dc.gov.

Latest News

Photo of inside Potomac Interceptor at Dulles showing newly lined tunnel

First of four emergency repairs on Potomac Interceptor finished

DC Water has finished the first of four emergency repair projects on the Potomac Interceptor sewer line. Crews completed work today to strengthen a 600-foot section of pipe at Dulles International Airport.

Picture of repaired segment before the geopolymer work and after the work is done

Crews also reach a major milestone near Dulles International Airport as the next phase of repairs begins this week

DC Water has completed the first major step in emergency repairs to a 175-foot section of the Potomac Interceptor near Pennyfield Lock in Potomac, Maryland. Crews added a new, stronger lining inside the pipe after inspections found serious wear and damage. The work is part of ongoing repairs to 1,700 linear feet of pipe near Pennyfield Lock. Work began on Friday to apply geopolymer, a concrete-like material, inside the pipe. With the new lining complete, crews are preparing for the next phase of work for the remainder of the pipe segment.

image of clara barton parkway with lane closure marked in red

Beginning this week and continuing through mid-August, DC Water will temporarily close one lane overnight on Clara Barton Parkway at the Maryland-D.C. border. The closures are needed so crews can ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Plastic bottles, cups and other floating debris on the surface of the Anacostia River before the Anacostia River Tunnel began operating.
Cleaner Waterways Start With Everyday Choices
Protecting our waterways starts with everyday actions and continues through critical infrastructure designed to keep pollution out of our rivers.
Upcoming Meeting

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.