SMALL DIAMETER WATER MAIN REPLACEMENT PROJECT CAPITOL HILL NEIGHBORHOOD III – ADVISORY NEIGHBORHOOD COMMISSION 6B

ADVISORY NEIGHBORHOOD COMMISSION 6B

Overview

As part of its Capital Improvement Program, DC Water is replacing existing 12-inch and smaller cast iron water mains in various locations throughout the city. Construction for this project will occur in the Capitol Hill neighborhood (see construction location map on the back). These efforts will help improve water quality and system reliability, increase water pressure in some areas, and maintain adequate flows throughout the system.

Scope of work

Installation of approximately 3,786 linear feet of 3-inch up to 12-inch water mainsReplacement of service lines – including free private side replacement of lead and galvanized iron pipeReplacement of fire hydrants and valvesRestoration of all surfaces disturbed by the project construction upon completion of work

Schedule

  • Construction start: On or about 11/11/2024
  • Construction completion: On or about 03/10/2025
  • Normal work hours: 7:00 AM to 5:00 PM, Monday through Friday

The contractor may, at times, need to work at night or on weekends, dependent upon certain construction activities or due to inclement weather.

Important information

For all planned temporary water service shut-offs, affected residents will be notified 48 hours in advance. Service interruptions should be minimal.Construction activities such as these may cause temporary discolored water or low water pressure. If you experience discolored water, it is recommended that you flush your cold water tap from the lowest point inside your property for approximately 15 minutes. If your water does not clear after this process, please contact DC Water’s Water Quality and Technology Division, or our 24-hr Emergency/Command Center.

Traffic

Flagging operations and lane closures may be required daily for each construction phase to maintain traffic in the construction work zone. All Traffic Control Plans will be approved by the District Department of Transportation (DDOT). At various times during construction, “No Parking” signs may be placed in certain areas in and around the work zone.  Notifications regarding “No Parking” zones will be posted 72 hours prior to construction, as required by DDOT.

Partners

DC Water is currently working closely with DDOT to ensure minimal traffic disruptions during this project. Regular updates will also be provided to impacted residents, Advisory Neighborhood Commission 6B, Ward 6 representatives in the Mayor’s Office of Community Relations and Services, and Ward 6 Councilmember Charles Allen and members of his staff.

Contact Information

FOR MORE INFORMATION, PLEASE CONTACT 

DC Water Project Manager
Christopher Szoch 
(336) 803-0955 
cszoch@hazenandsawyer.com 

DC Water Project Contractor
Capitol Paving of D.C. Inc. 
Raquel Flores
(202) 271-4131

DC Water Standard Contacts
Water Quality and Technology Division
(202) 612-3440 

24-hr Emergency/Command Center
(202) 612-3400

Office of Marketing and Communications
(202) 787-2200

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of Water Street and Capital Crescent Trail
TRAFFIC ADVISORY: Water Street NW at Georgetown Waterfront Park — Travel Lane and Sidewalk Closures

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT

Beginning on or about November 12, 2025, DC Water will begin preparing for construction on the Potomac River Tunnel on the 3300 block of Water Street NW, beneath the Whitehurst Freeway.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.