DC Water's Potomac River Tunnel Project to begin controlled underground blasting

May 01, 2025
DC Water Potomac River Tunnel Project construction site at West Potomac Park

As part of the excavation work for DC Water’s Potomac River Tunnel Project, weekly controlled underground blasting operations at the West Potomac Park construction site will begin as early as next week and continue through February 2026. The site is located along the Potomac River at Ohio Drive and Independence Avenue Southwest. All streets and sidewalks will remain open during blasting events, with no restrictions on boats or watercraft in the river.

The blasting operations are part of constructing two mining shafts needed to begin tunneling. These shafts, approximately 103 feet deep, will be used to lower and launch two tunnel boring machines (TBMs). These machines will construct the 5.5-mile tunnel. One TBM will excavate north, boring through rock to the endpoint at Georgetown University's entrance on Canal Road Northwest. The other will move south to the Joint-Base Anacostia Bolling (JBAB) site, where the Potomac River Tunnel connects with the Anacostia River Tunnel. The TBM excavating north, named Mary, will be delivered to the West Potomac Park site in the fall of 2025. The second TBM, called Emily, will be delivered in 2026.

What to Expect During Blasting Operations

  • Air horns will signal the start and completion of blasting operations.
  • Five minutes before the blast, an air horn will sound with three long signals.
  • One minute before the blast, the air horn will release five short signals.
  • The blast will detonate in a controlled manner.
  • Upon completion, one prolonged air horn signal will indicate the area is clear and safe.

Noise levels and ground vibrations will be closely monitored during this operation to ensure safety and compliance with the DC Fire and Emergency Medical Services Department, Metropolitan Police Department, and National Park Service. Residents and businesses in the vicinity may hear moderate noise during the blasting operations. Some mild ground vibrations may be felt in immediate work areas.

Project Details

The Potomac River Tunnel is the next major phase of DC Water’s Clean Rivers Project. The project consists of a large-diameter, deep sewer tunnel, diversion facilities, drop shafts, and support structures. The tunnel system will capture the combined overflow of wastewater and stormwater during major weather events until it can be released to the Blue Plains Advanced Wastewater Treatment Plant instead of being discharged into the Potomac River. The project is needed to reduce the sewer overflows to help improve the water quality of the Potomac River and, ultimately, Chesapeake Bay. The tunnel also ensures compliance with the 2005 Federal Consent Decree entered by DC Water, the District of Columbia, the US Environmental Protection Agency, and the US Department of Justice, as amended in January 2016.

When rainfall exceeds the sewer system’s capacity, the overflow is released at outlets into the Potomac River impacting water quality. An estimated 654 million gallons of mixed stormwater and sewage overflows enter the Potomac River in a year of average rainfall. The proposed controls are estimated to reduce the volume of untreated wastewater released into the Potomac River by 93% and reduce the frequency from approximately 74 events to only four times in a year of average rainfall.

Stay connected with us via the following channels: 

Project Email: dcpotomacrivertunnel@dcwater.com 
Project Website: dcwater.com/prt 
Dedicated Project Hotline: 202-972-1388 
DC Water 24-hour Emergency: 202-612-3400
 

Latest News

Workers putting down rye and matting for soil stabilization
  • More than one month after the last overflow into the Potomac River, DC Water is preparing to return flow in the coming days to the Potomac Interceptor and meet the mid-March target to complete the ...
Tree and debris removal for environmental rehabilitation

Work is nearly complete on the downstream section of the Potomac Interceptor to reinforce the pipeline with geopolymer. The concrete-like material will strengthen and restore the structural integrity of the pipe. Completion of the geopolymer lining downstream is one of the final steps to restore flow to the interceptor and finish the emergency repair.

This comes one month since the last overflow reached the Potomac River.

geopolymer downstream

As emergency repairs continue, today marks 27 days, nearly one month, with no overflow reaching the Potomac River.

Crews are making significant progress to reinforce the downstream section of pipe from the collapse site and completed 240 linear feet of geopolymer overnight. Crews are working to apply another layer of geopolymer today. The material is similar in strength to concrete and when applied restores the structural integrity of the pipe.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
March 11, 2026
Wednesday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.