DC Water Revises Canal Road Slope Stabilization Plan in Response to Community Feedback

July 24, 2025
Picture of previous rock slide on the slope

DC Water has revised its slope stabilization plan along Canal Road Northwest to significantly reduce traffic disruptions during construction. The updated approach eliminates the need for a full-time lane closure on a major commuter artery. The revised plan comes in response to community feedback and concerns from residents and commuters about the traffic impact.

DC Water weighed several options for the project stretching from Foxhall Road to the Georgetown University entrance. The new plan will keep all four lanes open while extending the project by more than a month. Due to safety concerns, a walkway through the construction zone cannot be provided. An ADA-accessible shuttle will remain available for those who prefer not to use the detour routes.

The original plan called for closing one lane of Canal Road and keeping the remaining three lanes open with one lane being reversible for rush hour traffic. This would have allowed DC Water to work from the bottom of the slope, using heavier equipment to accelerate construction and meet the timeline required under consent decree to complete the Potomac River Tunnel Project.

Under the new plan, construction is expected to begin in late August or early September and will take place from the top of the slope. Due to the steep terrain, smaller equipment is required, along with additional safety measures to prevent rockslides and manage erosion and runoff from above. As a result, the project timeline is expected to go from about 5 months to approximately 6.5 months.

About 14,500 vehicles use Canal Road between 6:00 a.m. and 7:00 p.m. daily, and any traffic disruption could impact M Street, Key Bridge, Whitehurst Freeway, and Chain Bridge. While normal two-way traffic will be maintained during most of the project, occasional off-peak lane closures will still be necessary for safety and equipment access.

Due to the sidewalk closure on the north side of Canal Road, pedestrians and cyclists will be detoured. The following routes are recommended for access between Foxhall Road, Georgetown, and points east:

Eastbound

  • Foundry Branch Tunnel → Capital Crescent Trail → Water Street NW→34th Street
  • Foundry Branch Tunnel → C & O Canal Towpath (via stairs from tunnel) →34th Street 

Westbound

  • 34th Street → Water Street → Capital Crescent Trail → Foundry Branch Tunnel
  • 34th Street → C & O Canal Towpath → Foundry Branch Tunnel (via stairs to tunnel) 
     

For some cyclists Reservoir Road may also be an option depending on the destination.

The revised plan balances community input and traffic flow with the need to meet the timeline for the Potomac River Tunnel project. Slope stabilization is critical to begin construction of a deep drop shaft and diversion facility which will help significantly reduce untreated sewage and stormwater entering the Potomac River—improving water quality for generations to come.

The Potomac River Tunnel is the next major phase of DC Water’s Clean Rivers Project. It includes a 5.5-mile-long, 18-foot-diameter tunnel designed to capture and convey combined sewer overflows (CSOs) to the Blue Plains Advanced Wastewater Treatment Plant. The project is required under a 2005 federal Consent Decree entered by DC Water, the District of Columbia, the U.S. Environmental Protection Agency, and the U.S. Department of Justice and amended in 2016.

DC Water thanks the community for its engagement and patience as we move forward with this important work.

For more information and updates, visit our Potomac River Tunnel page on dcwater.com.

 

Latest News

Aerial View of Construction near Watergate Complex Shows cranes and construction of drop shaft underway

Rock Creek and Potomac Parkway NW Beginning September 23, 2025, to Mid-November 2025

DC Water is installing temporary scaffolding at the Rock Creek Trail site, west of the Watergate Complex. Trail users are advised to adhere to flagger instructions during installation.

Scaffolding installation is expected to be completed by September 26, 2025, and will remain in place until mid-November 2025.

Canal Rd slope showing areas with fallen rock

Off-Peak Lane Closures and Sidewalk Closure Begin This Week

Starting, Saturday, September 20, DC Water will begin construction to stabilize the slope on Canal Road NW between Foxhall Road (Glover-Archbold Trailhead) and the Georgetown University (GU) entrance.

Photo of completed repair with concrete encasing the sewr pipe

DC Water has successfully completed emergency repairs on a critical section of the Anacostia Force Main following a failure near Anacostia Avenue and Ponds Street Northeast in July. With repairs finalized, attention now turns to rehabilitating other vulnerable segments of the 6.25-mile pipeline to ensure long-term reliability and resilience. 

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Aerial View of Construction near Watergate Complex Shows cranes and construction of drop shaft underway
Scaffolding Installation Begins near Watergate Complex for Potomac River Tunnel Project

Rock Creek and Potomac Parkway NW Beginning September 23, 2025, to Mid-November 2025

DC Water is installing temporary scaffolding at the Rock Creek Trail site, west of the Watergate Complex. Trail users are advised to adhere to flagger instructions during installation.

Scaffolding installation is expected to be completed by September 26, 2025, and will remain in place until mid-November 2025.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Sep 27
11:00 am - 7:00 pm
Sep 28
10:00 am - 2:00 pm
Sep 29
6:30 pm - 8:00 pm

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.