EMERGENCY WATER MAIN REPAIR
Feb 07, 2026 | 04:00 AM

EMERGENCY WATER MAIN REPAIR
Feb 07, 2026 | 03:00 AM

EMERGENCY WATER OUTAGE
Feb 07, 2026 | 01:16 AM

DC Water Revises Canal Road Slope Stabilization Plan in Response to Community Feedback

July 24, 2025
Picture of previous rock slide on the slope

DC Water has revised its slope stabilization plan along Canal Road Northwest to significantly reduce traffic disruptions during construction. The updated approach eliminates the need for a full-time lane closure on a major commuter artery. The revised plan comes in response to community feedback and concerns from residents and commuters about the traffic impact.

DC Water weighed several options for the project stretching from Foxhall Road to the Georgetown University entrance. The new plan will keep all four lanes open while extending the project by more than a month. Due to safety concerns, a walkway through the construction zone cannot be provided. An ADA-accessible shuttle will remain available for those who prefer not to use the detour routes.

The original plan called for closing one lane of Canal Road and keeping the remaining three lanes open with one lane being reversible for rush hour traffic. This would have allowed DC Water to work from the bottom of the slope, using heavier equipment to accelerate construction and meet the timeline required under consent decree to complete the Potomac River Tunnel Project.

Under the new plan, construction is expected to begin in late August or early September and will take place from the top of the slope. Due to the steep terrain, smaller equipment is required, along with additional safety measures to prevent rockslides and manage erosion and runoff from above. As a result, the project timeline is expected to go from about 5 months to approximately 6.5 months.

About 14,500 vehicles use Canal Road between 6:00 a.m. and 7:00 p.m. daily, and any traffic disruption could impact M Street, Key Bridge, Whitehurst Freeway, and Chain Bridge. While normal two-way traffic will be maintained during most of the project, occasional off-peak lane closures will still be necessary for safety and equipment access.

Due to the sidewalk closure on the north side of Canal Road, pedestrians and cyclists will be detoured. The following routes are recommended for access between Foxhall Road, Georgetown, and points east:

Eastbound

  • Foundry Branch Tunnel → Capital Crescent Trail → Water Street NW→34th Street
  • Foundry Branch Tunnel → C & O Canal Towpath (via stairs from tunnel) →34th Street 

Westbound

  • 34th Street → Water Street → Capital Crescent Trail → Foundry Branch Tunnel
  • 34th Street → C & O Canal Towpath → Foundry Branch Tunnel (via stairs to tunnel) 
     

For some cyclists Reservoir Road may also be an option depending on the destination.

The revised plan balances community input and traffic flow with the need to meet the timeline for the Potomac River Tunnel project. Slope stabilization is critical to begin construction of a deep drop shaft and diversion facility which will help significantly reduce untreated sewage and stormwater entering the Potomac River—improving water quality for generations to come.

The Potomac River Tunnel is the next major phase of DC Water’s Clean Rivers Project. It includes a 5.5-mile-long, 18-foot-diameter tunnel designed to capture and convey combined sewer overflows (CSOs) to the Blue Plains Advanced Wastewater Treatment Plant. The project is required under a 2005 federal Consent Decree entered by DC Water, the District of Columbia, the U.S. Environmental Protection Agency, and the U.S. Department of Justice and amended in 2016.

DC Water thanks the community for its engagement and patience as we move forward with this important work.

For more information and updates, visit our Potomac River Tunnel page on dcwater.com.

 

Latest News

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Three workers over the pit accessing the Potomac Interceptor for Cleaning

DC Water and its contractor are working to clean debris from a damaged section of the Potomac Interceptor, a sanitary sewer line that collapsed on January 19, along Clara Barton Parkway and the 495 ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.