Potomac River Tunnel Project

DC Water’s Potomac River Tunnel Project


The Potomac River Tunnel (PRT) is the next major phase of the DC Clean Rivers Project. The project consists of a large-diameter deep sewer tunnel, diversion facilities, drop shafts, and support structures to capture flows from existing combined sewer overflows (CSOs) along the Potomac River and convey them to the Blue Plains Advanced Wastewater Treatment Plant for treatment.

There are 8 CSO outfall locations on the Potomac River. In a year of average rainfall some 74 CSO events discharge approximately 654 million gallons of CSO into the Potomac. When complete, the PRT is estimated to reduce those events to four and reduce the volume of CSOs by 93% in an average rainfall year.

In 2019, DC Water began design work for the Potomac River Tunnel, and in 2024 began mobilization at West Potomac Park. When completed in 2030, the tunnel will improve water quality and aesthetics of the Potomac River for the benefit of all.

Watch DC Water lower Mary—the tunnel boring machine—deep underground. Check out our video.

Just The Facts
93 %
Reduction
OVERFLOW
To POTOMAC River
5.50
miles
Tunnel Length
18
Feet
Tunnel Diameter
100
Feet
Tunnel Depth
6.50
Years
Construction Duration
819
Million Dollars
Tunnel Cost

Stay connected with us through these convenient options:

Project Hotline 202-972-1388
Project Email dcpotomacrivertunnel@dcwater.com
Call DC Water Emergency Services for urgent water or sewer issues or to report a dry weather overflow at any time, 202-612-3400.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

DC Water Officials with NPS and ANC commissioners doing ceremonial groundbreaking
DC Water Breaks Ground on Piney Branch Tunnel, Final Phase of DC Clean Rivers Project

Today, DC Water broke ground on the Piney Branch Tunnel, the final major tunnel in our Clean Rivers Project. This work will help keep sewage and trash out of local waterways and make Rock Creek, the Potomac River, and the Chesapeake Bay cleaner for our community.

When we finish the Piney Branch Tunnel, it will hold at least 4.2 million gallons of rainwater and wastewater during heavy storms. Instead of overflowing into Piney Branch, that water will go to the Blue Plains Water Resource Recovery Facility, where it will be treated.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 13, 2026
Monday, 2:00 PM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.