Clean Rivers Green Infrastructure Projects at DC Water Facilities

Fort Reno Plants

Overview

As part of its Consent Decree requirements, DC Water implemented Green Infrastructure (GI) at DC Water facilities to reduce the volume of stormwater entering the combined sewer system. The GI implemented under this project includes:

  • Fort Reno Reservoir: 42,400 square feet of green roof and 8,400 square feet of pervious pavement
  • Anacostia Water Pumping Station: 1,000 square feet of pervious pavement and 1,500 square feet of bioretention
  • East Side Pumping Station: 6,600 square feet of green roof

These GI facilities were designed to capture precipitation from at least 90% of the storms in an average year. DC Water performs ongoing maintenance to ensure long-term performance of the facilities and pre/post-construction monitoring is providing data to improve future GI design, construction, operation and maintenance.

 

 

 

Schedule

Construction of GI at DC Water Facilities was completed in accordance with the Consent Decree schedule.  Ongoing regular maintenance activities began in January 2014 and continue today.

clean river
Clean Rivers

The Clean Rivers Project is DC Water's ongoing program to reduce combined sewer overflows into the District's waterways - the Anacostia and Potomac Rivers and Rock Creek. The Project is a massive infrastructure and support program designed to capture and clean water during heavy rainfalls before it ever reaches our rivers.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Photo of the drop shaft looking from above down into the bottom
Controlled Blasting to Begin for Potomac River Tunnel Work Near Georgetown

Starting the week of July 13, 2026, people who live, work or travel near the Canal Road NW entrance to Georgetown University may hear controlled blasting. This work is part of our Potomac River Tunnel Project.

When blasting happens, neighbors may hear a brief noise or feel light shaking. Drivers, cyclists, and pedestrians on Canal Road NW may also be stopped for a few minutes while we safely complete each blast.

Latest Blog Post
Five photos from the American Water Works Association (AWWA) ACE26 conference featuring panel discussions, technical presentations, networking, and attendees posing at the ACE26 display.
ACE26 Highlights: How DC Water Advanced the Conversation on Water
More than 80 DC Water employees joined thousands of water professionals in Washington, D.C., sharing expertise, building partnerships and advancing conversations that will help shape the future of water.
Upcoming Meeting
Date
July 8, 2026
Wednesday, 9:30 AM

Upcoming Events

Jul 23
Jul 25

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.