WASA Upgrades Georgetown Sewer System to Eliminate Sinkholes

January 29, 2008

Beginning this spring, Georgetown neighborhoods will be getting an upgrade to the aging underground sewer system that had been causing sinkholes in the area. In general, sinkholes are depressions or holes in the ground surface caused by the removal of soil or bedrock. Sinkholes may be formed gradually or suddenly. Often, sinkholes are caused by the soil entering an underground utility, such as a sewer main.

The sinkholes started to appear in Georgetown in late 2005, and immediate repairs were made as needed, but a comprehensive investigation uncovered structural defects in the aging sanitary sewer system from 29th to 31st streets, NW and from R to M streets, NW. The area was inspected visually and with television systems, which determined that 17 of the 29 combined sewers were defective.

With that information, WASA initiated the $1 million Georgetown Sewer Rehabilitation project. From the early stages of planning, WASA officials have worked closely with area residents and concerned citizens through the Advisory Neighborhood Commission 2E. “This project has been carefully planned to minimize impact to citizens and to traffic,” WASA General Manager Jerry N. Johnson explained. “We are only excavating where we absolutely must, and in all other instances we are leveraging advanced ‘trenchless’ technologies.”

One of these technologies, cured-in-place piping (CIPP), uses a resin-lined tube pulled inside the damaged pipe, then heated with steam or hot water. The heat “cures” the resin, creating a form-fitting, jointless, rehabilitated pipe. This process reduces the need for digging, since all of the pipe need not be exposed. Robotically controlled cutting devices and closed-circuit television are used for the service laterals.

The project includes construction and rehabilitation of approximately 2,535 linear feet of the existing sanitary sewer system, excavation in eight locations where pipes have been crushed, and rehabilitation of 28 sewer manholes, using an epoxy lining to further reduce the need for digging and to substantially increase the life of the manholes. Approximately 265 feet of the sewers could not be inspected prior to the repairs and will be inspected by closed-circuit television. Any work needed will be performed along with the rest of the project. The construction is slated for completion by early 2009.

Latest News

Picture of flow back in the Potomac Interceptor

DC Water Celebrates Massive 55-Day Effort, Outlines Next Steps for Rehabilitation and Environmental Restoration

After 55 days of extraordinary effort with crews working around the clock, DC Water has successfully completed emergency repairs and returned the flow to the Potomac Interceptor to mark a major milestone.

graphic with meeting times

Second Meeting Scheduled in Bethesda; Community Forum in Alexandria Next Week

As DC Water nears completion of emergency repairs on the Potomac Interceptor sewer line, we remain committed to transparent communication and partnership with our community. Next week, two meetings are scheduled on March 18, in Bethesda, MD and March 19, in Alexandria, VA to hear from the community and provide informational updates.

Photo of PI ready for return of flow
  • DC Water has completed final site preparations to return the flow to the Potomac Interceptor, marking and important milestone after 33 consecutive days without an overflow to the Potomac River.
  • The ...

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Map of lane closure
Traffic Advisory: Rock Creek and Potomac Parkway NW Lane Closure Beginning Jan 19

Beginning on or about January 19, 2026, weather permitting, DC Water will implement a temporary lane closure on Rock Creek and Potomac Parkway NW b

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
March 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 50% of the last 3 payments made. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.