Statement of Glenn S. Gerstell Chairman, Board of Directors DC Water and Sewer Authority on WASA Report

July 16, 2004

I want to thank Eric Holder and his colleagues at Covington & Burling for this comprehensive examination of WASA’s performance in discovering and dealing with issue of lead in the drinking water of some homes in the District.

When we learned about what happened, the WASA Board of Directors decided it wanted an independent and thorough investigation into how WASA handled the situation. And that is exactly what we got.

This Report is a complete and candid assessment of how some employees responsible for water quality at WASA mishandled the water testing program over a period of years, and how, as an organization, WASA failed to effectively communicate with the residents of the District of Columbia.

As Board Chairman and a District resident, I expect better. And I am confident that with operational and communications improvements already underway, as well as many of the recommendations offered by Mr. Holder, the residents of the District of Columbia will be better served by the Authority in the future.

While the Report is rightly critical of some in WASA’s organization, I want to make it clear that General Manager Jerry Johnson enjoys my confidence and I believe the confidence of the entire Board. I know he is committed to forthrightly addressing the deficiencies that have been identified in the Holder Report.

Clearly WASA made mistakes and down-played information in communications. But by no means does WASA bear sole responsibility for this problem. The Holder Report makes clear that the EPA was involved at every step along the way, provided inconsistent and shifting responses to WASA, and failed to see the problem until just a few months ago – long after this was a story in the media.

The Report cites instance after instance when the EPA, the Washington Aqueduct and the District of Columbia Department of Health were asleep at the switch. They all missed opportunities in the 2000-2001 and 2001-2002 monitoring periods to confront this problem, and after learning about the exceedance of lead action levels offered at best tepid responses.

And moving from our experience here in Washington to the national implications of the federal regulation in this area, it’s also obvious that the Lead and Copper Rule is ill-designed. The rule, and EPA's enforcement of it, and consequently, WASA's efforts to comply with it, were focused on how to achieve a passing score, not how to inform the public and how to truly and effectively address the underlying problem of lead levels in drinking water.

While the Report establishes that WASA followed 98% of the EPA’s rules in this area, it’s equally clear that even if WASA had complied 100% with the regulations, the District’s residents would still have lacked necessary information as well as recommendations to minimize exposure to lead in the water.

That’s why the Board has announced that we are going beyond the EPA requirements and addressing the problem head-on, in undertaking the nation’s largest program of removal of all lead pipes in public space. That action, together with the other corrective steps we will take in terms of WASA management and organization, will help ensure that this problem never occurs again.

The Board appreciates the work – both in the nature of the findings as well as in the recommendations – conducted by Mr. Holder and his staff and Professor Kathryn Newcomer of George Washington University and Dr. Lynn Goldman of the Johns Hopkins Bloomberg School of Public Health. I have already instructed each Board committee to examine both the Holder findings and recommendations and report back to the full Board about how and the extent to which those recommendations should be implemented.

Thank you and I look forward to your questions.

Latest News

Trench boxes at construction site for new pit accessing Potomac Interceptor Upstream

DC Water and its contractors continue to make progress constructing new access points to the Potomac Interceptor, one upstream of the damaged section, and an additional entry downstream to divert more wastewater flow from the pipe. These access points will allow crews to install a bulkhead, blocking flow in the pipe upstream of the collapsed area, keeping the site as dry as possible so crews can safely remove an extensive rock dam currently blocking the pipe.

Photo of giant rock and boulder removed

DC Water is releasing new findings regarding the environmental impacts following the January 19, collapse in a section of the Potomac Interceptor. Based on flow monitoring data collected before and after interim bypass pumping was activated, DC Water estimates approximately 243 million gallons of wastewater has overflowed from the collapse site.

Image of rock blockage taken by CCTV inside the Potomac Interceptor downstream of the collapse

Update on Extended Repairs, Safety Measures, and Water Quality Monitoring

Overnight CCTV inspection of the Potomac Interceptor revealed the blockage inside the collapsed sewer line is far more significant, showing a large rock dam stretching approximately 30 feet downstream of the original failure.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Picture of new bike pedestrian path and traffic detour
New Path for Capital Crescent Trail Opens at Georgetown Waterfront Park

DC CLEAN RIVERS – POTOMAC RIVER TUNNEL PROJECT
If you bike, drive, or walk through Georgetown, we’ve got changes starting this week around the Potomac River Tunnel construction on Water Street NW. The Capital Crescent Trail has a new temporary detour through Georgetown Waterfront Park, open now for cyclists between 33rd and Potomac streets NW.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting
Date
February 19, 2026
Thursday, 9:30 AM

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.