Westbound M Street Lane Closure Begins August 20

August 20, 2012

(Washington, DC) – DC Water will resume construction on M Street, NW as part of the Large Valve Replacements Project.

Beginning Monday, August 20, 2012 through Saturday, September 15, 2012, weather permitting, crews will be working in one westbound lane on M Street, NW near Key Bridge.

Crews will complete large valve replacement work, Monday through Friday, between the hours of 9:00 p.m. and 5:00 a.m.

Impacts:
* There will be closure of one westbound lane on M Street
during work hours.
* Excavation operations at the outset of the work will
require driving of piles into the ground, resulting in
extreme noise during abbreviated periods.
* Some traffic stops and delays within the vicinity of the
project area are anticipated.

Temporary traffic signs will be set up throughout the area to alert motorists to the upcoming lane closures.

###
About DC Water
The District of Columbia Water and Sewer Authority (DC Water), is an industry leading multi-jurisdictional regional utility that provides drinking water, wastewater collection and treatment to 600,000 residential, commercial and governmental customers in the District of Columbia, 17.8 million annual visitors and also collects and treats wastewater for 1.6 million customers in Montgomery and Prince Georges counties in Maryland and Fairfax and Loudoun counties in Virginia.

DC Water’s service area covers approximately 725 square miles and the company operates the world’s largest advanced wastewater treatment plant with a capacity of 370 million gallons per day and a peak capacity of 1.076 billion gallons per day.

Latest News

View of Independence Ave SW

(Washington, DC) –DC Water’s contractor on the Potomac River Tunnel Project will continue potholing operations along Independence Avenue, SW between Ohio Drive and West Basin Drive on or about April ...

Photo of CEO David Gadis and Chief Communications and Stakeholder Engagement Officer Kirsten Williams addressing the audience at a town hall meeting.

Authority Offers Virtual and In-Person Options

Photo shows an adult washing a glass in the sink with the faucet running.

The U.S. Army Corps of Engineers’ Washington Aqueduct, which supplies water to DC Water, annually performs a temporary disinfectant switch from chloramine to chlorine. This year, the switch runs from March 25 to May 6. During that time, customers may notice temporary minor changes in taste and odor.