Alerts
EMERGENCY WATER OUTAGE
4923 MASSACHUSETTS AVE NW BETWEEN 49TH ST NW & ALBEMARLE ST NWRead more >
INSPECTOR ON THE WAY
Low pressure to no water in the area of T St NE between Brentwood Rd NE & 9th St NERead more >
INSPECTOR ON THE WAY
Low pressure to no water in the area of T St NE between Brentwood Rd NE & 9th St NERead more >
See all Workzone Alerts

Spring Valley Water Main Upgrade Project

Overview

DC Water is performing water main upgrades within the Spring Valley neighborhood as part of its Capital Improvement Program. These upgrades are designed to improve water quality, system reliability, water pressure in some areas, and also ensure optimal fire flow.

Scope of work

  • Replacement of existing water main with a larger diameter water main in Rockwood Parkway NW
  • Installation of a new water main connection to an existing main in Nebraska Avenue NW
  • Structural lining of existing water mains in Woodway Lane, NW; Hillbrook Lane, NW; 49th Street, NW; and Glenbrook Road, NW

Schedule

  • Construction start: November 2017 (tentative) 
  • Construction completion: March 2019 

Important information

Spring Valley is located within a formerly used defense site, consisting of 661 acres in the northwest section of Washington, D.C. During World War I, the site was known as the American University Experiment Station. Since 1993, the U.S. Army Corps of Engineers (USACE) in partnership with the U.S. Environmental Protection Agency (EPA) and the District Department of Energy and the Environment (DOEE) has conducted extensive investigations and cleanup actions within the area. The bulk of the finds have been discarded military munitions and munitions debris that were mostly not fuzed and unfired. Confirmed unexploded ordnances (fuzed and fired) have not been found to date. The Army recently completed a multi-year effort to remove arsenic contaminated soil from several locations within the site. The site is not designated as a Superfund site.

Since the existing water mains were constructed after American University Experiment Station was closed, it is unlikely that any chemical warfare or explosive materials will be encountered during construction of the water main upgrades. However, because it is possible that such materials could be encountered, DC Water is working with the USACE, EPA, DOEE and District Department of Transportation (DDOT) to ensure public safety. DC Water has adopted a conservative approach to reduce risk, including performing soil testing by coring through the pavement and collecting samples for laboratory analysis; minimizing excavation by lining water mains where existing pipe size is adequate and replacing water mains in the same trench where pipe upsizing is needed; and having an unexploded ordnance specialist present.

DC Water will work to achieve minimal disruption during site investigations for design and construction and will restore the area to its original condition. Traffic control, including signage and protective barriers, will be set up to maintain public safety. In addition, DC Water will meet with the local Advisory Neighborhood Commission (ANC) and affected property owners to address public concerns.

Project location